⫸ If a project has a BCWS of $45,500,000 and a BCWP of $47,500,000 at the end of the 14th month of the project, what is the status of this project? Select one: a. The project is 4% ahead of schedule b. The project is 4% underbudget c. The project is 4% behind schedule d. The project is on schedule and on budget e. The project is 4% overbudge. Answer: a. The project is 4% ahead of schedule ⫸ In a WIP report, how do you calculate Revenue Earned? Select one: a. Given value, no need to calculate Revenue Earned b. (Revised Contract Amount) times (Percent Complete) c. (Cost to Date) divided by (Revised Estimated Costs) d. (Revised Contract Amount) minus (Revised Estimated Costs) e. (Billed to Date) minus (Revenue Earned). Answer: b. (Revised Contract Amount) times (Percent Complete) ⫸ A tool used by project managers to help control schedule performance is CPM Select one: True False. Answer: True ⫸ In earned value, if the planned percent complete value is less than the percent complete value, then the project is ahead of schedule Select one: True False. Answer: True ⫸ The Actual Cost of Work Performed is the Earned Value for a project Select one: True False. Answer: False ⫸ Value engineering typically cheapens the process by lowering costs and reducing the quality of a function Select one: True False. Answer: false

Content preview

CM 4221 EXAM COMPREHENSIVE
QUESTIONS AND ANSWERS ALL
CORRECT LATEST 2025 UPDATE.


⫸ If a project has a BCWS of $45,500,000 and a BCWP of $47,500,000 at
the end of the 14th month of the project, what is the status of this project?


Select one:
a. The project is 4% ahead of schedule
b. The project is 4% underbudget
c. The project is 4% behind schedule
d. The project is on schedule and on budget
e. The project is 4% overbudge. Answer: a. The project is 4% ahead of
schedule


⫸ In a WIP report, how do you calculate Revenue Earned?


Select one:
a. Given value, no need to calculate Revenue Earned
b. (Revised Contract Amount) times (Percent Complete)
c. (Cost to Date) divided by (Revised Estimated Costs)
d. (Revised Contract Amount) minus (Revised Estimated Costs)
e. (Billed to Date) minus (Revenue Earned). Answer: b. (Revised Contract
Amount) times (Percent Complete)

,⫸ A tool used by project managers to help control schedule performance is
CPM


Select one:
True
False. Answer: True


⫸ In earned value, if the planned percent complete value is less than the
percent complete value, then the project is ahead of schedule


Select one:
True
False. Answer: True


⫸ The Actual Cost of Work Performed is the Earned Value for a project


Select one:
True
False. Answer: False


⫸ Value engineering typically cheapens the process by lowering costs and
reducing the quality of a function


Select one:
True
False. Answer: false

, ⫸ Value is calculated by dividing the total of function and quality by the
cost


Select one:
True
Fals. Answer: True


⫸ One major barrier to the use of VE on construction projects is that VE is
not required on public or private projects.


Select one:
True
False. Answer: F


⫸ Which value analysis approach listed keeps the function and quality the
same while lowering the cost?


Select one:
a. Cost reduction approach
b. Compound approach
c. Expand growth approach
d. None of these
e. Function increase approach. Answer: a. Cost reduction approach



⫸ What is the definition of a project delivery system?


Select one:

Document information

Uploaded on
June 14, 2025
Number of pages
27
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers
$11.99

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
TopGradeInsider
4.2
(13)
Sold
161
Followers
2
Items
54906
Last sold
1 day ago



Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions