QUESTION 1
What is used to solicit a quotation from the contractor for a proposed change to
the project scope? - ANSWERS-Change order request
QUESTION 2
What is submitted by the contractor in response to a field order OR as an
uninitiated request for a change in scope? - ANSWERS-Change order
QUESTION 3
What is the formal document that defines the required changes in project scope
and identifies the associated changes to the time frame, the dollar amounts, or
both? - ANSWERS-Change order
QUESTION 4
What summarizes the corrections that a contractor must make prior to the work
being accepted as complete? - ANSWERS-Punch list
END OF
PAGE
1
, RTPM EXAM LATEST
QUESTION 5
What is a form of communication between the contractor and owner defining the
specifics of how a job will be undertaken? - ANSWERS-Submittals
QUESTION 6
The construction industry has two common components to submittals which are:
_______ and ________. - ANSWERS-Shop drawings & Manufacturer's product
data sheet
QUESTION 7
Who provides shop drawings? - ANSWERS-Specialty contractors such as: HVAC
or Fire Safety
QUESTION 8
What are used for documenting the specific equipment or products provided on
the job? - ANSWERS-product data sheets/ cut sheets
END OF
PAGE
2
, RTPM EXAM LATEST
QUESTION 9
List two action submittals required by the cabling installation team. - ANSWERS-
Products & Shop drawings
QUESTION 10
List three products that are action submittals for the cabling installation team. -
ANSWERS-firestop, cable or outlets.
QUESTION 11
List three items that could be included in shop drawings. - ANSWERS-equipment
rack placement or cable routing.
QUESTION 12
What document is used to track action submittals? - ANSWERS-back board
layouts
END OF
PAGE
3
, RTPM EXAM LATEST
QUESTION 13
The as-built version of the drawings that are used to construct the building and
prepared from the record copy drawings can be integrated or incorporated into the
___________________. - ANSWERS-Computer aided facility management
system (CAFM)
QUESTION 14
What is made well after occupancy and once the owner deems the project is
complete? - ANSWERS-Final payments and release of retainage amounts
QUESTION 15
During post-construction phase, who accepts responsibility for the operation of the
building - ANSWERS-Owner
QUESTION 16
What three elements are included in telecommunications designs? - ANSWERS-
Specifications, drawings, cost estimates
END OF
PAGE
4
ANSWER ALL QUESTIONS IN THIS SECTION
QUESTION 1
What is used to solicit a quotation from the contractor for a proposed change to
the project scope? - ANSWERS-Change order request
QUESTION 2
What is submitted by the contractor in response to a field order OR as an
uninitiated request for a change in scope? - ANSWERS-Change order
QUESTION 3
What is the formal document that defines the required changes in project scope
and identifies the associated changes to the time frame, the dollar amounts, or
both? - ANSWERS-Change order
QUESTION 4
What summarizes the corrections that a contractor must make prior to the work
being accepted as complete? - ANSWERS-Punch list
END OF
PAGE
1
, RTPM EXAM LATEST
QUESTION 5
What is a form of communication between the contractor and owner defining the
specifics of how a job will be undertaken? - ANSWERS-Submittals
QUESTION 6
The construction industry has two common components to submittals which are:
_______ and ________. - ANSWERS-Shop drawings & Manufacturer's product
data sheet
QUESTION 7
Who provides shop drawings? - ANSWERS-Specialty contractors such as: HVAC
or Fire Safety
QUESTION 8
What are used for documenting the specific equipment or products provided on
the job? - ANSWERS-product data sheets/ cut sheets
END OF
PAGE
2
, RTPM EXAM LATEST
QUESTION 9
List two action submittals required by the cabling installation team. - ANSWERS-
Products & Shop drawings
QUESTION 10
List three products that are action submittals for the cabling installation team. -
ANSWERS-firestop, cable or outlets.
QUESTION 11
List three items that could be included in shop drawings. - ANSWERS-equipment
rack placement or cable routing.
QUESTION 12
What document is used to track action submittals? - ANSWERS-back board
layouts
END OF
PAGE
3
, RTPM EXAM LATEST
QUESTION 13
The as-built version of the drawings that are used to construct the building and
prepared from the record copy drawings can be integrated or incorporated into the
___________________. - ANSWERS-Computer aided facility management
system (CAFM)
QUESTION 14
What is made well after occupancy and once the owner deems the project is
complete? - ANSWERS-Final payments and release of retainage amounts
QUESTION 15
During post-construction phase, who accepts responsibility for the operation of the
building - ANSWERS-Owner
QUESTION 16
What three elements are included in telecommunications designs? - ANSWERS-
Specifications, drawings, cost estimates