MAN 4583 Exam 2 Questions with Correct Answers Graded A+ What is a Project Network - Answers A flow chart that graphically depicts the sequence, interdependencies, and start and finish times of the project job plan of activities that is the critical path through the network. What are some of the things to be considered in the critical path? - Answers scheduling labor and equipment communication project's duration budgeting cash flow Identifies critical activities What is an activity? - Answers An element of the project that requires time. What is a merge activity? - Answers An activity that has two or more preceding activities on which it depends. What is a burst activity? - Answers An activity that has more than one activity immediately following it (more than one dependency arrow flowing from it). What is a parallel (concurrent) activity? - Answers Activities that can occur independently and, if desired, not at the same time. What is a path? - Answers a sequence of connected, dependent activities. What is a critical path? - Answers the longest path through the activity network that allows for the completion of all project-related activities; the shortest expected time in which the entire project can be completed. Delays on the critical path will delay completion of the entire project. What is an event? - Answers a point in time when an activity is started or completed. It does not consume time. What are the two different approaches? - Answers Activity-on-Node (AON) & Activity-on-Arrow (AOA) What is an Activity-on-Node (AON)? - Answers It uses a node to depict an activity What is an Activity-on-Arrow (AOA)? - Answers It uses an arrow to depict an activity What are the basic rules to follow in developing project networks? - Answers 1. Flow from left to right 2. An activity cannot begin until all preceding connected activities are complete 3. Arrows indicate precedence and flow and can cross over each other. 4. Each activity must have a unique identify number that is greater than any of its predecessor activities. 5. Looping is not allowed. 6. Conditional statements are not allowed. 7. Use common start and stop nodes. What is the forward pass computation? - Answers Add activity times along each path in the network (ES + Duration = EF). Carry the early finish (EF) to the next activity where it becomes its early start (ES) unless... The next succeeding activity is a merge activity, in which case the largest EF of all preceding activities is selected. What is the backward pass computation? - Answers Subtract activity times along each path in the network (LF - Duration = LS). Carry the late start (LS) to the next activity where it becomes its late finish (LF) unless The next succeeding activity is a burst activity, in which case the smallest LF of all preceding activities is selected. What is free slack (float)? - Answers Is the amount of time an activity can be delayed after the start of a longer parallel activity or activities. Is how long an activity can exceed its early finish date without affecting early start dates of any successor(s). Allows flexibility in scheduling scarce resources. What is sensitivity? - Answers The likelihood the original critical path(s) will change once the project is initiated. How do you determine the critical path with free slack? - Answers The critical path is the network path(s) that has (have) the least slack in common. What are the practical considerations for networking? - Answers Network Logic Errors Activity Numbering Use of Computers to Develop Networks Calendar Dates What is laddering? - Answers Activities are broken into segments so the following activity can begin sooner and not delay the work. What are lags? - Answers The minimum amount of time a dependent activity must be delayed to begin or end.

Content preview

MAN 4583 Exam 2 Questions with Correct Answers Graded A+

What is a Project Network - Answers A flow chart that graphically depicts the sequence,
interdependencies, and start and finish times of the project job plan of activities that is the critical path
through the network.

What are some of the things to be considered in the critical path? - Answers scheduling labor and
equipment

communication

project's duration

budgeting cash flow

Identifies critical activities

What is an activity? - Answers An element of the project that requires time.

What is a merge activity? - Answers An activity that has two or more preceding activities on which it
depends.

What is a burst activity? - Answers An activity that has more than one activity immediately following it
(more than one dependency arrow flowing from it).

What is a parallel (concurrent) activity? - Answers Activities that can occur independently and, if desired,
not at the same time.

What is a path? - Answers a sequence of connected, dependent activities.

What is a critical path? - Answers the longest path through the activity network that allows for the
completion of all project-related activities; the shortest expected time in which the entire project can be
completed. Delays on the critical path will delay completion of the entire project.

What is an event? - Answers a point in time when an activity is started
or completed. It does not consume time.

What are the two different approaches? - Answers Activity-on-Node (AON) & Activity-on-Arrow (AOA)

What is an Activity-on-Node (AON)? - Answers It uses a node to depict an activity

What is an Activity-on-Arrow (AOA)? - Answers It uses an arrow to depict an activity

What are the basic rules to follow in developing project networks? - Answers 1. Flow from left to right

2. An activity cannot begin until all preceding connected activities are complete

, 3. Arrows indicate precedence and flow
and can cross over each other.

4. Each activity must have a unique identify number that is greater than any of its predecessor activities.

5. Looping is not allowed.

6. Conditional statements are not allowed.

7. Use common start and stop nodes.

What is the forward pass computation? - Answers Add activity times along each path in the network (ES
+ Duration = EF).

Carry the early finish (EF) to the next activity where it becomes its early start (ES) unless...

The next succeeding activity is a merge activity, in which case the largest EF of all preceding activities is
selected.

What is the backward pass computation? - Answers Subtract activity times along each path in the
network (LF - Duration = LS).

Carry the late start (LS) to the next activity where it becomes its late finish (LF) unless

The next succeeding activity is a burst activity, in which case the smallest LF of all preceding activities is
selected.

What is free slack (float)? - Answers Is the amount of time an activity can be delayed after the start of a
longer parallel activity or activities.

Is how long an activity can exceed its early finish date without affecting early start dates of any
successor(s).

Allows flexibility in scheduling scarce resources.

What is sensitivity? - Answers The likelihood the original critical path(s) will change once the project is
initiated.

How do you determine the critical path with free slack? - Answers The critical path is the network
path(s) that has (have) the least slack in common.

What are the practical considerations for networking? - Answers Network Logic Errors

Activity Numbering

Use of Computers to Develop Networks

Calendar Dates

Document information

Uploaded on
June 13, 2025
Number of pages
13
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers
$10.89

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
TutorJosh
3.4
(74)
Sold
485
Followers
16
Items
32709
Last sold
3 days ago



Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions