MIS 416 EXAM 2 QUESTIONS WITH COMPLETE
SOLUTIONS
_____ monitoring results gives organizations the capability to
maintain awareness of the risk being incurred, highlight the need
to revisit other steps in the risk management process, and initiate
process improvement activities as needed. Correct Answers
analyzing
A best practice for enabling a risk mitigation plan from your risk
assessment is prioritizing countermeasures.
T/F Correct Answers T
A best practice for enabling a risk mitigation plan from your risk
assessment is staying within scope.
T/F Correct Answers T
A business impact analysis (BIA) is an output of the risk
assessment process.
T/F Correct Answers F
A CBA helps determine if you should use a safeguard.
T/F Correct Answers T
A decision is made to accept, avoid, transfer, or mitigate a risk is
done in the risk evaluation stage.
,T/F Correct Answers T
A gap analysis report documents differences between what is
mitigated and what is NOT mitigated, resulting in a gap in
security.
T/F Correct Answers T
A KPx is a summary of one or more KRIs.
T/F Correct Answers F
A risk ____ could be a simple listing of identified risks, some of
which are already assessed and others of which are still in the
process of being qualified
A. Assessment
B. Plan
C. Mitigation
D. Inventory Correct Answers D
A risk assessment ends with a report.
T/F Correct Answers T
A risk assessment provides a point-in-time report.
,T/F Correct Answers T
A threshold KPI is significant when an index falls into a set
range.
T/F Correct Answers T
Access controls testing verifies user rights and permissions.
T/F Correct Answers T
Action plans are a necessary output of the risk assessment
process so that recommendations can be acted upon quickly
once the assessment is approved.
T/F Correct Answers T
After you collect data on risks and recommendations, you
include that information in a report, and you give that report to
management. Why do you do this?
A. to help management assess how much of the risk was
mitigated by the proposed solution
B. to help management decide which recommendations to use
C. to avoid several time-consuming presentations about each
individual recommendation
, D. to inform management of the progress of the risk
management task Correct Answers B
ALE is:
A. SLE / ARO
B. SLE x ARO
C. SLE - ARO
D. ARO * EF Correct Answers B
All of the following are KPI types except:
A. Milestone
B. Qualitative
C. Esoteric
D. Threshold Correct Answers C
All of the following are risk treatments in different frameworks
except?
SOLUTIONS
_____ monitoring results gives organizations the capability to
maintain awareness of the risk being incurred, highlight the need
to revisit other steps in the risk management process, and initiate
process improvement activities as needed. Correct Answers
analyzing
A best practice for enabling a risk mitigation plan from your risk
assessment is prioritizing countermeasures.
T/F Correct Answers T
A best practice for enabling a risk mitigation plan from your risk
assessment is staying within scope.
T/F Correct Answers T
A business impact analysis (BIA) is an output of the risk
assessment process.
T/F Correct Answers F
A CBA helps determine if you should use a safeguard.
T/F Correct Answers T
A decision is made to accept, avoid, transfer, or mitigate a risk is
done in the risk evaluation stage.
,T/F Correct Answers T
A gap analysis report documents differences between what is
mitigated and what is NOT mitigated, resulting in a gap in
security.
T/F Correct Answers T
A KPx is a summary of one or more KRIs.
T/F Correct Answers F
A risk ____ could be a simple listing of identified risks, some of
which are already assessed and others of which are still in the
process of being qualified
A. Assessment
B. Plan
C. Mitigation
D. Inventory Correct Answers D
A risk assessment ends with a report.
T/F Correct Answers T
A risk assessment provides a point-in-time report.
,T/F Correct Answers T
A threshold KPI is significant when an index falls into a set
range.
T/F Correct Answers T
Access controls testing verifies user rights and permissions.
T/F Correct Answers T
Action plans are a necessary output of the risk assessment
process so that recommendations can be acted upon quickly
once the assessment is approved.
T/F Correct Answers T
After you collect data on risks and recommendations, you
include that information in a report, and you give that report to
management. Why do you do this?
A. to help management assess how much of the risk was
mitigated by the proposed solution
B. to help management decide which recommendations to use
C. to avoid several time-consuming presentations about each
individual recommendation
, D. to inform management of the progress of the risk
management task Correct Answers B
ALE is:
A. SLE / ARO
B. SLE x ARO
C. SLE - ARO
D. ARO * EF Correct Answers B
All of the following are KPI types except:
A. Milestone
B. Qualitative
C. Esoteric
D. Threshold Correct Answers C
All of the following are risk treatments in different frameworks
except?