NCCCO TEST PREP
1. What should an operator do if a crane load mo- Cease crane operation, and report
ment indicator malfunction? the condition to the supervisor
2. Where are the standard method hand signals ASME B30.R.
found?
3. What happens to the leverage of the load on Increases
crane as the boom is being lowered?
4. When is it OK to temporarily bypass the cranes During assembly and disassembly
overload warning system? operation
5. What capacity should you use when the boom A length estimated between the
length of the crane falls between the length list- length in the charts
ed in the low chart?
6. What action does signal person intends to oper- Boom up
ator to perform if he extends his arm and shoul-
der height, makes a fist his hand, and sticks his
or her thumb up?
7. When hoisting personnel within what percent- 1%
age of level muscle telescopic boom crane be in
order for the girls reading in low chart remain
valid?
8. What is the net capacity of a crane unless the The capacity listed in a low chart,
manufacturer states otherwise? minimize the weight of the rigging
and all attachment
9. What may happen to a properly reload when lift It could swing out away from the
off the ground unless operator takes account of crane
boom deflection?
, NCCCO TEST PREP
10. Who should've operator respond to a "stop" sig- Anyone
nal from?
11. Which area do truck cranes without a 5th outrig- front
ger generally have no lifting capacity unless the
manufacturer states otherwise?
12. According to federal requirements, under what never
conditions is it okay for a person to ride the
headache ball?
13. What percentage do most manufacturers re- 20%
quire a cranes load charge capacity to be re-
duced for duty cycle operation such as high vol-
ume concrete placement
14. From which two point should the boom be mea- From the boom hinge pins to the
sured? center of the boom tip sheave
15. What is the preferred method of installing wire The rope runs from the top of the
rope from a reel onto a hoist drum? Rio to the top of the drum
16. Over rich Quadrant our truck cranes, capacities, Over the rear
usually greater?
17. according to OSHA, which assessable area of an Swing radius of the rear of the ro-
operating crane must be barricaded? tating structure
18. What is OSHA's regulation governing cranes in 1926.1400
construction?
19. Under which circumstances is a crack in the If it's cause on no visible distortion
windshield of a crane cab is okay? that would interfere with safe oper-
ations
1. What should an operator do if a crane load mo- Cease crane operation, and report
ment indicator malfunction? the condition to the supervisor
2. Where are the standard method hand signals ASME B30.R.
found?
3. What happens to the leverage of the load on Increases
crane as the boom is being lowered?
4. When is it OK to temporarily bypass the cranes During assembly and disassembly
overload warning system? operation
5. What capacity should you use when the boom A length estimated between the
length of the crane falls between the length list- length in the charts
ed in the low chart?
6. What action does signal person intends to oper- Boom up
ator to perform if he extends his arm and shoul-
der height, makes a fist his hand, and sticks his
or her thumb up?
7. When hoisting personnel within what percent- 1%
age of level muscle telescopic boom crane be in
order for the girls reading in low chart remain
valid?
8. What is the net capacity of a crane unless the The capacity listed in a low chart,
manufacturer states otherwise? minimize the weight of the rigging
and all attachment
9. What may happen to a properly reload when lift It could swing out away from the
off the ground unless operator takes account of crane
boom deflection?
, NCCCO TEST PREP
10. Who should've operator respond to a "stop" sig- Anyone
nal from?
11. Which area do truck cranes without a 5th outrig- front
ger generally have no lifting capacity unless the
manufacturer states otherwise?
12. According to federal requirements, under what never
conditions is it okay for a person to ride the
headache ball?
13. What percentage do most manufacturers re- 20%
quire a cranes load charge capacity to be re-
duced for duty cycle operation such as high vol-
ume concrete placement
14. From which two point should the boom be mea- From the boom hinge pins to the
sured? center of the boom tip sheave
15. What is the preferred method of installing wire The rope runs from the top of the
rope from a reel onto a hoist drum? Rio to the top of the drum
16. Over rich Quadrant our truck cranes, capacities, Over the rear
usually greater?
17. according to OSHA, which assessable area of an Swing radius of the rear of the ro-
operating crane must be barricaded? tating structure
18. What is OSHA's regulation governing cranes in 1926.1400
construction?
19. Under which circumstances is a crack in the If it's cause on no visible distortion
windshield of a crane cab is okay? that would interfere with safe oper-
ations