Exam questions with verified answers
-Hydration Ans✓✓✓ A chemical reaction between Portland cement
and water that causes concrete to harden to a stone-like condition -
Exothermic Reaction
· A project will: Ans✓✓✓ o Not be part of ongoing day to day business.
o Involve notable risk.
o Be significantly impacted upon failure of activities.
Have at least 2 people or elements working together
· Airfield Damage Repair (ADR): Ans✓✓✓ o Process: Gain Security,
Assess Site, Clear Site, Mark Site, Prepare Site, Repair Site using one of
the techniques
· Bridge Classification:
o Rapid Field Classification Booklet Ans✓✓✓ Provides a rapid field
method of establishing bridge capacity in the field, but only as a
temporary measure.
· GE is utilized in support of: Ans✓✓✓ o Defense- Continuously
conducted to harden and prepare positions, facilities, installations
o Offense- Providing assured mobility of forces from ports of
debarkation to forward AOs
,o Stability- Focus is likely GE capabilities applied to restore essential
services and support infrastructure development
· Heliport Categories: Assault Heliport Ans✓✓✓ -Service Life is 1-4
weeks
-Normally Semi-Prepared/Unsurfaced
-Designed for
-Observation aircraft
-Utility Aircraft
-Attack Aircraft
· Heliport Categories: Initial Ans✓✓✓ -might begin with an insertion of
Engineers to clear (LZs) for individual aircraft or LZs of opportunity.
Usage:
-Individual Aircraft
-LZ of opportunity
LZ expanded into Semi-prepared and Surfaced as require
· Heliport Categories: Initial Ans✓✓✓ -Unsurfaced
-Located anywhere in T/O, mostly in areas that sustain close combat
-Little or no construction effort
-May not meet desired safety criteria
-Hazardous, inefficient and limited to good weather and visibility
,-No estimated service life
· Node Time Estimate: Ans✓✓✓ o Forward Pass: (Early Start) +
(Duration) = (Early Finish)
o Backward Pass: (Late Finish) - (Duration) = (Late Start)
* Quality Control (QC) 2 Levels Ans✓✓✓ •Unit QC Program
•Project QC Plan
*5 Data Elements of construction activities Ans✓✓✓ Resources
NSNs
Drawings
Support Files
TOGS
-Just remember that there are five
*Authorized Party for contracted design changes Ans✓✓✓ Contracting
Officer is the only Authorized party to approve design changes
*PWS Performance Work Statement Ans✓✓✓ A form of a statement
of work, emphasizing measurable performance requirements to
describing specifications and requirements
, 4 Base Camp Planning Principles Ans✓✓✓ o Scalability
o Sustainability
o Standardization
o Survivability
4 Compartments of Engineer Units in operating force Ans✓✓✓ There
are 4 complementary and interdependent categories of Engineer Units
in the operating force: Unified Action Partners, USAES, Army Corps of
Engineers, and USACE...these include organic engineers, EN HQs,
baseline EN units, and specialized EN units.
6 Warfighting Functions Ans✓✓✓ movement and maneuver,
intelligence, fires, sustainment, command and control, and protection
8 Steps to Basecamp Planning Process Ans✓✓✓ -1 Preliminary
Planning- analyzing everything about the mission
-2 Location Selection - Where do you want to build this?
-3 Land Use Planning- 12 steps to calculate, map, and plan allocation of
land and areas.
-4 Facility Requirements Developments- 8 steps to translate facility
allowance information into terms that prospective users can
understand.
-5 General Site Planning- Planning where everything will go based on
info provided