2025/2026 Exam Questions Marking
Scheme New Update | A+ Rated
1) When is the BEST time to document each loop check for commissioning
? A. Prior to the start of inspection
B. When all test and inspection activities are complete
C. When updating information on a daily basis
D. At the time each test is completed - 🧠 ANSWER ✔✔D. At the time each
test is completed (INST LVL4)(12410-16/ Section 3.2.0)
2) Teflon paste must not be used on :
A. Nitrogen service
B. Natural gas service
C. Water service
D. Oxygen service - 🧠 ANSWER ✔✔D. Oxygen service (INST LVL 1
)(12109-14/Section 2.1.1)
1
COPYRIGHT©PROFFKERRYMARTIN 2025/2026. YEAR PUBLISHED 2025. COMPANY REGISTRATION NUMBER: 619652435. TERMS OF USE.
PRIVACY STATEMENT. ALL RIGHTS RESERVED
,3) A 24VDC power supply is not working . With your multimeter you verify
no DC voltage . On the 120VAC input you measure 120V between hot and
ground , and 72V between hot and neutral . What is the most likely cause
of this ?
A. Lost the ground
B. Lost the hot
C. Lost the neutral
D. Lost the fuse - 🧠 ANSWER ✔✔C. Lost the neutral
4) Gain increase when tube :
A. Back bends are made
B. Bend radius increases
C. Size decreases
D. Long radius elbows are used - 🧠 ANSWER ✔✔B. Bend radius increases
(INST LVL 2)(12302-15 section 2.1.1)
5) A temperature measuring device that produces a voltage as the
temperature changes is a / an :
A. RTD
2
COPYRIGHT©PROFFKERRYMARTIN 2025/2026. YEAR PUBLISHED 2025. COMPANY REGISTRATION NUMBER: 619652435. TERMS OF USE.
PRIVACY STATEMENT. ALL RIGHTS RESERVED
,B. Thermistor
C. Thermometer
D. Thermocouple - 🧠 ANSWER ✔✔D. Thermocouple (INST LVL 2) (12110-
15 section 1.2.2)
6) A pressure piping code is found in :
A. ANSI B 31.1
B. NEC 690 .
C. OSHA1910 .
D. ISA S 5.1 - 🧠 ANSWER ✔✔A. ANSI B 31.1
7) When marking tubing for cutting , the preferred method is
A. Scribe a mark into the tube with a sharp object .
B. Mark the tube with a grease pencil
C. Mark the tube with a felt tip pen
D. Mark the tube with a crayon - 🧠 ANSWER ✔✔C. Mark the tube with a felt
tip pen
8) An example of direct measurement indicator is a :
3
COPYRIGHT©PROFFKERRYMARTIN 2025/2026. YEAR PUBLISHED 2025. COMPANY REGISTRATION NUMBER: 619652435. TERMS OF USE.
PRIVACY STATEMENT. ALL RIGHTS RESERVED
, A. Pressure gauge
B. Bulb thermometer
C. Sight glass
D. Flowmeter - 🧠 ANSWER ✔✔C. Sight glass
9) On the image , how many hand valves are installed on Tank 1201C
A. 1
B. 2
C. 3
D. 4 - 🧠 ANSWER ✔✔C. 3
10) What is the first step in troubleshooting a problem in a system ?
A. Turn off power to the instrument
B. Stimulate an input
C. Verify that there is a problem
D. Stimulate an output - 🧠 ANSWER ✔✔C. Verify that there is a problem
11) Where can the appropriate elevation of an instrument be found ?
A. Location drawing
4
COPYRIGHT©PROFFKERRYMARTIN 2025/2026. YEAR PUBLISHED 2025. COMPANY REGISTRATION NUMBER: 619652435. TERMS OF USE.
PRIVACY STATEMENT. ALL RIGHTS RESERVED