Pg. 1 Copyright © 2025 Jasonmcconell. ALL RIGHTS RESERVED. ENCE325 Exam 2025 Questions and Answers The widening of a state highway is an example of which sector of the construction industry? [Commercial, Industrial, Residential, Infrastructure] - ANS Infrastructure Specialty trade contractors are typically hired on the job by? - ANS The contractor A construction project is characterized by the following? [It uses resources, It is unique, It results in deliverables or All of the above] - ANS All of the above In which of the following stages does the contractor have the major responsibility to coordinate all necessary tasks associated with that stage? [Design, Programming, Feasibility, Close-out] - ANS close-out Which member of the contractor's team is responsible for the day-to-day production activities on the jobsite? - ANS The superintendent The residential sector of the industry is characterized by which of the following? [Buildings are typically publicly financed, Projects are fairly low tech, Projects typically use steel and concrete building materials, Projects are typically designed by engineers] - ANS projects are fairly low tech What is the major rating system for green buildings - ANS LEED

Content preview

ENCE325 Exam 2025 Questions and
Answers



The widening of a state highway is an example of which sector of the construction industry?
[Commercial, Industrial, Residential, Infrastructure] - ANS Infrastructure



Specialty trade contractors are typically hired on the job by? - ANS The contractor


A construction project is characterized by the following? [It uses resources,

It is unique, It results in deliverables or All of the above] - ANS All of the above


In which of the following stages does the contractor have the major responsibility to coordinate
all necessary tasks associated with that stage? [Design, Programming, Feasibility, Close-out] -
ANS close-out


Which member of the contractor's team is responsible for the day-to-day production activities
on the jobsite? - ANS The superintendent


The residential sector of the industry is characterized by which of the following? [Buildings are
typically publicly financed, Projects are fairly low tech, Projects typically use steel and concrete
building materials, Projects are typically designed by engineers] - ANS projects are fairly low
tech



What is the major rating system for green buildings - ANS LEED



Pg. 1 Copyright © 2025 Jasonmcconell. ALL RIGHTS RESERVED.

, During the start-up and mobilization stage the following activities occur? - ANS The
contractor moves onto the jobsite



The Owner is responsible for the project feasibility stage. (True or False) - ANS true


According to Dykstra, there are 3 outcomes of the bidding and award stage. They include all,
except which of the following? [Award of construction contract, bid submittals by contractors,
bid review, bid package] - ANS Bid Review


A design-build delivery method typically results in the owner having one contract with the
architect and another contract with the contractor. (True or False) - ANS False


The owner will decide which of the following as a result of the feasibility stage (select all correct
answers). [Ask the Architect to fund the project
Move forward with project, Abandon the project, Adjust the scope, budget, and/or schedule,
Ask the Contractor to design the project] - ANS Move forward with project, abandon the
project, adjust the scope, budget and schedule


Project design typically occurs in three distinct phases: Answer in order of design and phase
progression - ANS Schematic Design, Design Development and Construction Documents


An owner is considering building a 120 unit housing development on the outskirts of town.
What would you refer to in determining if livestock would be allowed as part of the property
development? - ANS Zoning Ordinance


Private owners may prefer to negotiate a fixed price with a contractor. In that situation, the
delivery method is called - ANS Design Negotiate Build (DNB)


In an agency construction management (agency CM) delivery method, the CM is financially
responsible and self-performs work. (True or False) - ANS False

Pg. 2 Copyright © 2025 Jasonmcconell. ALL RIGHTS RESERVED.

Document information

Uploaded on
May 22, 2025
Number of pages
6
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers
$11.99

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
StarGuide
4.4
(5)
Sold
21
Followers
0
Items
2586
Last sold
4 months ago



Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions