Studio 2 | Estimating Exam | 114 Questions with Complete Solutions | 2025–2026 Update

Document preview thumbnail
Preview 3 out of 19 pages

This document is a comprehensive compilation of 114 graded questions and correct answers for the Studio 2 Estimating Exam, updated for the 2025–2026 academic period. It covers key estimating principles in construction such as quantity takeoff, bidding types, contract documents, labor and equipment productivity, excavation calculations, concrete and masonry estimating, and related legal and financial considerations. The content is ideal for students or professionals preparing for exams or needing a solid review of estimating fundamentals.

Content preview

1 | Page


STUDIO 2 - ESTIMATING EXAM | 114 QUESTIONS |
WITH COMPLETE SOLUTIONS/NEWEST UPDATE
Questions and Correct Answers/ Latest Update /
Already Graded
This provides the general contractor an acceptable rate of return and
compensation for the risk associated with the project. Choose the ONE best
answer.

Ans: Profit Margin


A detailed estimate determines the quantity and cost of everything required for
the project including: Select All that Apply.

Ans: Bonds, Insurance, Overhead, Labor, Materials


Square foot estimates may be adjusted for: Choose the ONE best answer.

Ans: Building Height


Quantity takeoff skills include: Choose the ONE best answer.

Ans: Reading and quantifying plans


Types of bids include: Choose the ONE best answer.

Ans: Competitive and Negotiated bids


Contract documents include: Choose the ONE best answer.

Ans: Technical specifications and drawings


The best source of estimating information is: Choose the ONE best answer.



© 2025/ 2026 | ® All rights reserved

, 2 | Page

Ans: Historical Data


Types of Agreements include: Select All that Apply.

Ans: Lump Sum, Unit-Price, Cost-Plus-Fee


Agreement Provisions include: Choose the ONE best answer.

Ans: All the answers shown


The type of bond which guarantees payment on another party's obligations is a
_________ bond. Choose the ONE best answer.

Ans: Surety


The type of bond which guarantees that the contractor will perform all the work
in accordance with the contract documents is a _______ bond. Choose the ONE
best answer.

Ans: Performance


________________ insurance provides benefits for workers injured or killed on
the job. Choose the ONE best answer.

Ans: Worker's Compensation


Real property includes: Choose the ONE best answer.

Ans: All the answers shown


Instruction to bidders include which procedures: Choose the ONE best answer.

Ans: All the answers shown



© 2025/ 2026 | ® All rights reserved

, 3 | Page

Which of the following statement is correct? Choose the ONE best answer.

Ans: The advantage of the percentage fee is that it allows the owner to save
fees paid to the contractor when construction costs go down.


Document ________ should be brought to the attention of the architect or
engineer. Choose the ONE best answer.

Ans: Errors


The required level of accuracy coupled with the amount of information about the
project that is available will dictate the type of estimate that can be prepared.
Which of the following is a correct order for estimating methods from lower to
higher accuracy and time to complete? Choose the ONE best answer.

Ans: Project Comparison - Square Foot - Parametric - Model - Assembly -
Detailed


To be able to do quantity takeoffs, the estimator must _____________. Choose
the ONE best answer.

Ans: All the answers shown


___________________ is a drawing or information that modifies the basic
contract documents after they have been issued to the bidder, but prior to the
taking of bids. They may provide clarification, correction, or changes in the other
documents. Choose the ONE best answer.

Ans: Addenda


In a _______________ agreement, the contractor agrees to construct the
project in accordance with the contract documents, for a set price arrived at
through competitive bidding or negotiation. The contractor agrees that the work



© 2025/ 2026 | ® All rights reserved

Document information

Uploaded on
May 15, 2025
Number of pages
19
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers
$14.49

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
Expert1
4.1
(9)
Sold
68
Followers
3
Items
7651
Last sold
6 days ago



Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions