CORB EXAM STUDY GUIDE
7 Clauses in which ACO may modify construction contracts - Answers :1. Variation in
Estimate Quantity
2. Differing Site Conditions
3. Suspension of Work
4. Changes
5. Value Engineering - Construction
6. Default
7. Changes and Changed Conditions (purchase orders)

4 checks for ACO to issue a mod - Answers :1. Is the absolute value of the change
within warrant threshold of $500K?
2. Is the change for a construction contract?
3. Is the change within the scope of the contract?
4. Is the change governed by any of the 7 authorized clauses?

ACO Appointment Letter - Answers :Letter from the Contracting Officer that authorizes
the ACO to obligate the government only within the monetary and other limitations
delegated to them for a specific contract.

Variation in Estimated Quantity Defined - Answers :If the quantity of a unit-priced item in
this contract is an estimated quantity and the actual quantity of the unit-priced item
varies more than 15 percent above or below the estimated quantity, an equitable
adjustment in the contract price shall be made upon demand of either party.

Variation in Estimated Quantity Clause - Answers :When a fixed-price construction
contract is contemplated that authorizes a variation in the estimated quantity of unit-
priced items

Variation in Estimated Quantity Rule of Thumb - Answers :Consider economy of scale
rule of thumb when evaluating variation in estimated quantity proposals. Increase in
quantity should decrease unit price

Differing Site Conditions - Answers :Clause which allows contractor to seek equitable
adjustment if conditions are found to differ materially from what is indicated in the
contract or normally encountered

Differing Site Conditions Type 1 - Answers :(1) Subsurface or latent physical conditions
at the site which differ materially from those indicated in this contract

Differing Site Conditions Type 2 - Answers :(2) Unknown physical conditions at the site,
of an unusual nature, which differ materially from those ordinarily encountered and
generally recognized as inhering in work of the character provided for in the contract.

, Differing Site Conditions Contractor Responsibilities - Answers :(a) The Contractor shall
promptly, and before the conditions are disturbed, give a written notice to the
Contracting Officer

(d) No request by the Contractor for an equitable adjustment to the contract for differing
site conditions shall be allowed if made after final payment under this contract.

Differing Site Conditions Government Responsibilities - Answers :(b) The Contracting
Officer shall investigate the site conditions promptly after receiving the notice. If the
conditions do materially so differ and cause an increase or decrease in the Contractor's
cost of, or the time required for, performing any part of the work under this contract,
whether or not changed as a result of the conditions, an equitable adjustment shall be
made under this clause and the contract modified in writing accordingly.

Suspension of Work - Answers :The Contracting Officer may order the Contractor, in
writing, to suspend, delay, or interrupt all or any part of the work of this contract for the
period of time that the Contracting Officer determines appropriate for the convenience of
the Government.

What type of modifications do not include profit? - Answers :Suspension of work clause
- (b) If the performance of all or any part of the work is, for an unreasonable period of
time, suspended, delayed, or interrupted (1)by an act of the Contracting Officer in the
administration of this contract, or (2)by the Contracting Officer's failure to act within the
time specified in this contract (or within a reasonable time if not specified), an
adjustment shall be made for any increase in the cost of performance of this contract
(excluding profit) necessarily caused by the unreasonable suspension, delay, or
interruption, and the contract modified in writing accordingly.

A claim under the Suspension of Work clause shall not be allowed- - Answers :(1) For
any costs incurred more than 20 days before the Contractor shall have notified the
Contracting Officer in writing of the act or failure to act involved

What 4 things can be modified under the Changes Clause - Answers :Changes can be
made to the following:
(1) In the specifications (including drawings and designs);
(2) In the method or manner of performance of the work;
(3) In the Government-furnished property or services; or
(4) Directing acceleration in the performance of the work.

What is considered a change order under the Changes Clause? - Answers :Any other
written or oral order (which, as used in this paragraph (b), includes direction, instruction,
interpretation, or determination) from the Contracting Officer that causes a change shall
be treated as a change order under this clause; Provided, that the Contractor gives the
Contracting Officer written notice stating-
(1) The date, circumstances, and source of the order; and
(2) That the Contractor regards the order as a change order.

Document information

Uploaded on
May 6, 2025
Number of pages
6
Written in
2024/2025
Type
Other
Person
Unknown
$13.49

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
GEEKA
3.8
(379)
Sold
2227
Followers
1451
Items
62985
Last sold
17 hours ago



Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions