When is the CSI/CSC UniFormat most often used?
a. During project conception and schematic design
b. In the procurement stage
c. In the facility management phase
d. Throughout the project life cycle, to organize information by materials and methods a.
During project conception and schematic design
The general contract clauses that establish payment responsibilities are found in:
a. General Conditions
b. Division 01 General Requirements
c. Payment bond
d. Addenda a. General Conditions
An example of a UniFormat Level 3 classification is:
,a. G Site work
b. D20 Plumbing
c. B2070 Exterior Louvers and Vents
d. All of the above c. B2070 Exterior Louvers and Vents
The contractual relationship governed by the Conditions of the Contract is between:
a. Owner and contractor
b. Architect/engineer and contractor
c. Owner and Subcontractors
d. Owner, contractor, and architect/engineer a. Owner and contractor
A unit price contract or contract portion is used when:
a. Extent of work cannot be fully determined or where actual quantities cannot be accurately
calculated.
b. Extent of work is known, but the owner desires a break-out cost for portions of the work.
c. It is anticipated that bidders will not examine soil-bearing reports prior to submitting the bid.
, d. Bidding quantities of equipment. a. Extent of work cannot be fully determined or where
actual quantities cannot be accurately calculated.
Instructions for Procurement:
a. Are used only on private projects
b. Frequently are standard industry forms
c. May include the geotechnical report as an attachment
d. Are binding upon the Contractor b. Frequently are standard industry forms
Which of the following would be included in Available Information?
a. Bid security requirements
b. Environmental Impact Statement
c. Time of completion to construct the project
d. Description of the Work b. Environmental Impact Statement
Marked-up or corrected contract drawings that indicate changes incorporated in the Work are: