Utah Contractor Exam (Real) Questions and Answers 100% Pass Depreciation is taken on which of the company's assets? a. Loans b. Current assets c. Fixed assets d. None of the above - C ... Explanation: Depreciation is counted from fixed assets. A private employer who employs __ or more people as of July 1, 2010, may not hire a new employee unless the employer is registered with and uses a status verification system such as E -Verify to verify the federal legal working status of any new employee. a. 5 b. 10 c. 15 d. 1 - C ... Explanation: A private employer who employs 15 or more people as of July 1, 2010, may not hire a new employee unless the employer is registered with and uses a status verification system such as E -Verify to verify the federal legal working status of any new employee. If a contractor decides to increase the contract price, the contractor: a. Should get a loan from the bank 2COPYRIGHT © 2025 BY SOPHIA BENNETT, ALL RIGHTS RESERVED b. May request assistance from the subcontractor c. And the owner must agree to a written and signed change order d. Should request the building inspector to revise the specifications - C ... Explanation: A written and signed change order can allow the contractor to change a contract price. If a subcontractor signs an unconditional waiver and release, this would imply that a: a. Subcontractor cannot ask anything more of the owner b. Owner cannot ask anything more of the subcontractor c. Subcontractor cannot get anything from the prime d. Subcontractor cannot ask anything more of the prime - A ... Explanation: Once the subcontractor signs an unconditional waiver and release, the subcontractor cannot ask anything more of the owner. Any applicant who has been denied a license to practice on the basis of credentials, or failure to pass a required examination, may submit a request for agency review to the executive director ____ following notification of the denial of a license or refusal to renew or reinstate a license. a. Within 10 days b. Within 20 days c. Within 30 days d. Within 60 days - 5. C ... Explanation: Any applicant who has been denied a license to practice on the basis of credentials, character, or failure to pass a required examination, or who has been refused renewal or reinstatement of a license to practice on the basis that the applicant does not meet qualifications for continued licensure in any occupation or profession under the jurisdiction of the division may submit a request for agency review to the executive director within 30 days 3COPYRIGHT © 2025 BY SOPHIA BENNETT, ALL RIGHTS RESERVED following notification of the denial of a license or refusal to renew or reinstate a license. What should a contractor do if after starting a home improvement project the contractor discovers that the details and specifications do NOT correctly show the existing construction? a. Stop and work on a correction b. Stop the job and inform the owner or his agent c. Continue the work if variations are only minor d. Stop the job and inform the Building Department - B ... Explanation: Any details and specifications are not represented correctly then it is the contractor's duty to inform the owner or his agent. Keeping good accounting records is important for: a. Maintaining financial statements b. Obtaining financing c. Effective management d. All of the above - D ... Explanation: Effective management, maintaining financial statements and obtaining proper financing are all the result of keeping good accounting records. 8. The promise by a party called the guarantor to make good the mistake, debt, or default of another party found in the construction contract law is called: a. Surety b. Guarantee c. Warrantee d. Agreement - B ... Explanation: Guarantee. 9. The plans and specifications of a home improvement project usually describe: 4COPYRIGHT © 2025 BY SOPHIA BENNETT, ALL RIGHTS RESERVED a. Layout sizes b. Liquidated damages c. Consent to arbitrate d. Neighborhood regulations - 9. A ... Explanation: Layout sizes are usually described in plans and specifications of home improvement projects. The number of years that an employer must keep records of FUTA and other federal taxes is: a. 2 years b. 4 years c. 6 years d. 10 years - B ... Explanatio

Content preview

Utah Contractor Exam (Real)
Questions and Answers 100% Pass


Depreciation is taken on which of the company's assets?

a. Loans

b. Current assets

c. Fixed assets

d. None of the above - ✔✔C ... Explanation: Depreciation is counted from fixed
assets.

A private employer who employs __ or more people as of July 1, 2010, may not hire
a new employee unless the employer is registered with and uses a status verification
system such as E -Verify to verify the federal legal working status of any new
employee.

a. 5

b. 10

c. 15

d. 1 - ✔✔C ... Explanation: A private employer who employs 15 or more people as of
July 1, 2010, may not hire a new employee unless the employer is registered with
and uses a status verification system such as E -Verify to verify the federal legal
working status of any new employee.

If a contractor decides to increase the contract price, the contractor:

a. Should get a loan from the bank


COPYRIGHT © 2025 BY SOPHIA BENNETT, ALL RIGHTS RESERVED 1

,b. May request assistance from the subcontractor

c. And the owner must agree to a written and signed change order

d. Should request the building inspector to revise the specifications - ✔✔C ...
Explanation: A written and signed change order can allow the contractor to change a
contract price.

If a subcontractor signs an unconditional waiver and release, this would imply that
a:

a. Subcontractor cannot ask anything more of the owner

b. Owner cannot ask anything more of the subcontractor

c. Subcontractor cannot get anything from the prime

d. Subcontractor cannot ask anything more of the prime - ✔✔A ... Explanation: Once
the subcontractor signs an unconditional waiver and release, the subcontractor
cannot ask anything more of the owner.

Any applicant who has been denied a license to practice on the basis of credentials,
or failure to pass a required examination, may submit a request for agency review to
the executive director ____ following notification of the denial of a license or refusal
to renew or reinstate a license.

a. Within 10 days

b. Within 20 days

c. Within 30 days

d. Within 60 days - ✔✔5. C ... Explanation: Any applicant who has been denied a
license to practice on the basis of credentials, character, or failure to pass a required
examination, or who has been refused renewal or reinstatement of a license to
practice on the basis that the applicant does not meet qualifications for continued
licensure in any occupation or profession under the jurisdiction of the division may
submit a request for agency review to the executive director within 30 days




COPYRIGHT © 2025 BY SOPHIA BENNETT, ALL RIGHTS RESERVED 2

,following notification of the denial of a license or refusal to renew or reinstate a
license.

What should a contractor do if after starting a home improvement project the
contractor discovers that the details and specifications do NOT correctly show the
existing construction?

a. Stop and work on a correction

b. Stop the job and inform the owner or his agent

c. Continue the work if variations are only minor

d. Stop the job and inform the Building Department - ✔✔B ... Explanation: Any
details and specifications are not represented correctly then it is the contractor's duty
to inform the owner or his agent.

Keeping good accounting records is important for:

a. Maintaining financial statements

b. Obtaining financing

c. Effective management

d. All of the above - ✔✔D ... Explanation: Effective management, maintaining
financial statements and obtaining proper financing are all the result of keeping
good accounting records.

8. The promise by a party called the guarantor to make good the mistake, debt, or
default of another party found in the construction contract law is called:

a. Surety

b. Guarantee

c. Warrantee

d. Agreement - ✔✔B ... Explanation: Guarantee.

9. The plans and specifications of a home improvement project usually describe:



COPYRIGHT © 2025 BY SOPHIA BENNETT, ALL RIGHTS RESERVED 3

, a. Layout sizes

b. Liquidated damages

c. Consent to arbitrate

d. Neighborhood regulations - ✔✔9. A ... Explanation: Layout sizes are usually
described in plans and specifications of home improvement projects.

The number of years that an employer must keep records of FUTA and other federal
taxes is:

a. 2 years

b. 4 years

c. 6 years

d. 10 years - ✔✔B ... Explanation: 4 years is the amount of time an employer must
keep records of FUTA and other federal taxes.




Page: 5-2

What is the term for a detailed compilation of the quantity of each elemental work
item?

a. Summary sheet

b. Bid invitation

c. Takeoff

d. Specification - ✔✔C ... Explanation: Estimators use construction blueprints, either
manually or electronically, and start "taking off" quantities of items they will need
from those blueprints in order to prepare part of the estimate.




Page: 6-3




COPYRIGHT © 2025 BY SOPHIA BENNETT, ALL RIGHTS RESERVED 4

Document information

Uploaded on
April 20, 2025
Number of pages
168
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers
$13.99

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
SophiaBennett
3.6
(29)
Sold
156
Followers
5
Items
9092
Last sold
1 week ago




Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions