A project estimator is developing a cost estimate for construction of a new
diagnostic imaging wing. The projected costs are:
Fixed equipment installation charges $700,000
Site isolation $50,000
Annual utilities $425,000
Construction materials $1,200,000
Portable equipment $900,000
Annual depreciation $275,000
What are the expected contractor expenses? - ✔✔1,600,000
Which of the following contribute to typical general contractor fees:
COPYRIGHT © 2025 BY SOPHIA BENNETT, ALL RIGHTS RESERVED 1
,1. Permit and inspection fees
2. General conditions
3. Overhead and profit
4. Site condition assessment fees - ✔✔2, 3, and 4
Demand side management (DSM) programs are developed and offered to
organizations by energy providers to do which of the following during peak service?
- ✔✔Provide emergency energy demand sources
When developing a preventive maintenance program, a facility manager should
ensure that an annual test is conducted on every required battery-powered lighting
system. This test should be run for NOT less than: - ✔✔30 seconds
In existing facilities, doors that open onto exit corridors should have 1-3/4 inch solid
bonded wood core or be of construction that resists fire for NOT less than: - ✔✔20
minutes
Total dissolved solids in a cooling tower are regulated by: - ✔✔Variable speed drive
fans
What contracts requires a schedule of values when negotiating? - ✔✔Guaranteed
maximum price
A project has a budget of $6,600,000. Planning and design fees are estimated at
$700,000 and construction expenses are estimated at $5,100,000. What is the amount
of a 10% construction contingency? - ✔✔580,000
COPYRIGHT © 2025 BY SOPHIA BENNETT, ALL RIGHTS RESERVED 2
, The Joint Commission standards require that an organization develop and
implement a policy to prohibit smoking except in specified circumstances. The
standard is intended to reduce risks of:
1. Possible adverse effects on care, treatment, and services to people who smoke
2. Passive smoke to others
3. Fire
4. False alarms - ✔✔2, 3, and 4
When planning demolition, construction, or renovation, an organization selects and
implements proper controls to reduce risk and minimize the impact of these
activities on infection control. Which of the following are proper controls within the
construction area:
1. Providing negative air machines
2. Installing dust barriers
3. Wet-mopping the floors
4. Ensuring debris-free job site - ✔✔2, 3, and 4