✔✔The general contract clauses that establish payment responsibilities are found in:
a. General Conditions
b. Division 01 General Requirements
c. Payment bond
d. Addenda - ✔✔a. General Conditions
✔✔An example of a UniFormat Level 3 classification is:
a. G Site work
b. D20 Plumbing
c. B2070 Exterior Louvers and Vents
d. All of the above - ✔✔c. B2070 Exterior Louvers and Vents
✔✔The contractual relationship governed by the Conditions of the Contract is between:
a. Owner and contractor
b. Architect/engineer and contractor
c. Owner and Subcontractors
d. Owner, contractor, and architect/engineer - ✔✔a. Owner and contractor
✔✔A unit price contract or contract portion is used when:
a. Extent of work cannot be fully determined or where actual quantities cannot be
accurately calculated.
b. Extent of work is known, but the owner desires a break-out cost for portions of the
work.
c. It is anticipated that bidders will not examine soil-bearing reports prior to submitting
the bid.
d. Bidding quantities of equipment. - ✔✔a. Extent of work cannot be fully determined or
where actual quantities cannot be accurately calculated.
✔✔Instructions for Procurement:
a. Are used only on private projects
b. Frequently are standard industry forms
c. May include the geotechnical report as an attachment
d. Are binding upon the Contractor - ✔✔b. Frequently are standard industry forms
✔✔Which of the following would be included in Available Information?
a. Bid security requirements
b. Environmental Impact Statement
, c. Time of completion to construct the project
d. Description of the Work - ✔✔b. Environmental Impact Statement
✔✔Marked-up or corrected contract drawings that indicate changes incorporated in the
Work are:
a. Contract forms
b. Closeout submittals
c. Record drawings
d. As-builts
e. Not required for private work - ✔✔c. Record drawings
✔✔Submittal requirements for Facility Services Divisions 21 through 28 are specified in:
a. The first section in each respective division
b. Supplementary Conditions
c. Division 01 Section "Submittal Procedures"
d. Section 01 12 00 Summary of Multiple Contracts - ✔✔c. Division 01 Section
"Submittal Procedures"
✔✔Contractual clauses in the Conditions of the Contract:
a. Have priority over Division 01
b. Are superseded by Division 01
c. Are expanded upon by the provisions of Division 01
d. Are independent, and Division 01 provisions have no effect - ✔✔c. Are expanded
upon by the provisions of Division 01
✔✔When outside consultants are responsible for the production of major portions of the
project specifications:
a. One design team member should be responsible for overall specification coordination
b. Different document formats should be used to identify the work of the separate
consultants
c. The lead design professional should avoid the liability inherent in reviewing
consultants' work
d. Information should be collected and the project A/E assume responsibility for
preparing each section - ✔✔a. One design team member should be responsible for
overall specification coordination
✔✔In the specifications, the stated requirements address:
a. The owner's responsibilities
b. The contractor's responsibilities
c. The subcontractor's responsibilities
d. The architect's responsibilities
ANSWERS GRADED A+
✔✔The general contract clauses that establish payment responsibilities are found in:
a. General Conditions
b. Division 01 General Requirements
c. Payment bond
d. Addenda - ✔✔a. General Conditions
✔✔An example of a UniFormat Level 3 classification is:
a. G Site work
b. D20 Plumbing
c. B2070 Exterior Louvers and Vents
d. All of the above - ✔✔c. B2070 Exterior Louvers and Vents
✔✔The contractual relationship governed by the Conditions of the Contract is between:
a. Owner and contractor
b. Architect/engineer and contractor
c. Owner and Subcontractors
d. Owner, contractor, and architect/engineer - ✔✔a. Owner and contractor
✔✔A unit price contract or contract portion is used when:
a. Extent of work cannot be fully determined or where actual quantities cannot be
accurately calculated.
b. Extent of work is known, but the owner desires a break-out cost for portions of the
work.
c. It is anticipated that bidders will not examine soil-bearing reports prior to submitting
the bid.
d. Bidding quantities of equipment. - ✔✔a. Extent of work cannot be fully determined or
where actual quantities cannot be accurately calculated.
✔✔Instructions for Procurement:
a. Are used only on private projects
b. Frequently are standard industry forms
c. May include the geotechnical report as an attachment
d. Are binding upon the Contractor - ✔✔b. Frequently are standard industry forms
✔✔Which of the following would be included in Available Information?
a. Bid security requirements
b. Environmental Impact Statement
, c. Time of completion to construct the project
d. Description of the Work - ✔✔b. Environmental Impact Statement
✔✔Marked-up or corrected contract drawings that indicate changes incorporated in the
Work are:
a. Contract forms
b. Closeout submittals
c. Record drawings
d. As-builts
e. Not required for private work - ✔✔c. Record drawings
✔✔Submittal requirements for Facility Services Divisions 21 through 28 are specified in:
a. The first section in each respective division
b. Supplementary Conditions
c. Division 01 Section "Submittal Procedures"
d. Section 01 12 00 Summary of Multiple Contracts - ✔✔c. Division 01 Section
"Submittal Procedures"
✔✔Contractual clauses in the Conditions of the Contract:
a. Have priority over Division 01
b. Are superseded by Division 01
c. Are expanded upon by the provisions of Division 01
d. Are independent, and Division 01 provisions have no effect - ✔✔c. Are expanded
upon by the provisions of Division 01
✔✔When outside consultants are responsible for the production of major portions of the
project specifications:
a. One design team member should be responsible for overall specification coordination
b. Different document formats should be used to identify the work of the separate
consultants
c. The lead design professional should avoid the liability inherent in reviewing
consultants' work
d. Information should be collected and the project A/E assume responsibility for
preparing each section - ✔✔a. One design team member should be responsible for
overall specification coordination
✔✔In the specifications, the stated requirements address:
a. The owner's responsibilities
b. The contractor's responsibilities
c. The subcontractor's responsibilities
d. The architect's responsibilities