Setback brequirements b(Wells band bSprings) b- bcorrect banswers✔✔a bmin bof b50' bfrom
bseptic btank band bmin b100' bfrom babsorption bfield
Setback brequirements b(Property blines) b- bcorrect banswers✔✔a bmin bof b10' bfrom
bseptic btanks, bmin bof b5' bfrom babsorption bfields bfor bproperty bon bpublic bwater
Setback brequirements b(bodies bof bwater bor bimpoundments) b- bcorrect banswers✔✔a
bmin bof b25' bfrom bseptic btanks band ba bmin bof b50' bfrom babsorption bfields
Setback brequirements b(streams band btributaries) b- bcorrect banswers✔✔a bmin bof b25'
bfrom bseptic btanks band ba bmin bof b50' bfrom babsorption bfields
Setback brequirements b(ponded bwetlands) b- bcorrect banswers✔✔a bmin b50' bfor
babsorption bfields
Setback brequirements b(buildings bwith ba bbasement) b- bcorrect banswers✔✔require
bseptic band babsorption bfields bmin bof b10'
Setback brequirements b(buildings bwithout ba bbasement) b- bcorrect banswers✔✔require
ban babsorption bfield bplacement ba bmin bof b5' bfrom bthe bfoundation
Setback brequirements b(drainage bditch) b- bcorrect banswers✔✔septic btanks bmust bbe
b15' bfrom bdrainage bditch
absorption bfields bmin bof b15' bfrom btrash bpits band bembankments
If bthe bwater bsupply bline bcrosses bor bcomes bwithin b10 bfeet bof bthe babsorption bfield,
b- bcorrect banswers✔✔the bwater bsupply
line bshall bbe binstalled bat bleast b12 binches babove bthe btop bof bthe baggregate blayer bof
bthe babsorption
field bline band bshall bbe bencased bin bsingle-length blarger bdiameter bwater bpipe, bsuch
bas b2" bPVC
All bseptic btanks, bpre-cast bor bpoured bin bplace, b- bcorrect banswers✔✔contain bat
bleast b2/3 bof bthe
total bliquid bcapacity bof bthe btank
Correct Answers
Setback brequirements b(Wells band bSprings) b- bcorrect banswers✔✔a bmin bof b50' bfrom
bseptic btank band bmin b100' bfrom babsorption bfield
Setback brequirements b(Property blines) b- bcorrect banswers✔✔a bmin bof b10' bfrom
bseptic btanks, bmin bof b5' bfrom babsorption bfields bfor bproperty bon bpublic bwater
Setback brequirements b(bodies bof bwater bor bimpoundments) b- bcorrect banswers✔✔a
bmin bof b25' bfrom bseptic btanks band ba bmin bof b50' bfrom babsorption bfields
Setback brequirements b(streams band btributaries) b- bcorrect banswers✔✔a bmin bof b25'
bfrom bseptic btanks band ba bmin bof b50' bfrom babsorption bfields
Setback brequirements b(ponded bwetlands) b- bcorrect banswers✔✔a bmin b50' bfor
babsorption bfields
Setback brequirements b(buildings bwith ba bbasement) b- bcorrect banswers✔✔require
bseptic band babsorption bfields bmin bof b10'
Setback brequirements b(buildings bwithout ba bbasement) b- bcorrect banswers✔✔require
ban babsorption bfield bplacement ba bmin bof b5' bfrom bthe bfoundation
Setback brequirements b(drainage bditch) b- bcorrect banswers✔✔septic btanks bmust bbe
b15' bfrom bdrainage bditch
absorption bfields bmin bof b15' bfrom btrash bpits band bembankments
If bthe bwater bsupply bline bcrosses bor bcomes bwithin b10 bfeet bof bthe babsorption bfield,
b- bcorrect banswers✔✔the bwater bsupply
line bshall bbe binstalled bat bleast b12 binches babove bthe btop bof bthe baggregate blayer bof
bthe babsorption
field bline band bshall bbe bencased bin bsingle-length blarger bdiameter bwater bpipe, bsuch
bas b2" bPVC
All bseptic btanks, bpre-cast bor bpoured bin bplace, b- bcorrect banswers✔✔contain bat
bleast b2/3 bof bthe
total bliquid bcapacity bof bthe btank