• Wrong document? Swap it for free
  • Written by students who passed
  • Immediately available after payment
  • Read online or as PDF
Sell
Where do you study
Your language
Document preview thumbnail
Preview 4 out of 38 pages
Exam (elaborations)

Construction Management on scheduling (e.g., CPM and PERT) 2

Document preview thumbnail
Preview 4 out of 38 pages

Construction Management on scheduling (e.g., CPM and PERT) 2

Content preview

1. In PERT analysis, if the optimistic time is 3 days, the most likely time is 5 days,

and the pessimistic time is 7 days, what is the expected time for the activity?

A. 5 days

B. 4 days

C. 5.5 days

D. 4.33 days

Answer: D) 4.33 days

Rationale and Working Out:

Using the PERT formula for expected time:

TE=O+4M+P6TE = \frac{O + 4M + P}{6}TE=6O+4M+P

Where:

• O = Optimistic time = 3

• M = Most likely time = 5

• P = Pessimistic time = 7

TE=3+4(5)+76=3+20+76=306=5 days.TE = \frac{3 + 4(5) + 7}{6} = \frac{3 + 20 +

7}{6} = \frac{30}{6} = 5 \text{ days}.TE=63+4(5)+7=63+20+7=630=5 days.

,2. In a project with multiple dependent tasks, which of the following methods helps to

identify the longest path of tasks, dictating the project’s duration?

A. Gantt chart

B. Resource leveling

C. Critical Path Method (CPM)

D. Monte Carlo simulation

Answer: C) Critical Path Method (CPM)

Rationale:

The Critical Path Method (CPM) is used to identify the longest path of dependent

tasks, which dictates the shortest possible duration to complete the project.




3. In PERT analysis, the standard deviation of an activity is given by:

A. P−O6\frac{P - O}{6}6P−O

B. O+P2\frac{O + P}{2}2O+P

C. P+O+M3\frac{P + O + M}{3}3P+O+M

D. M−O6\frac{M - O}{6}6M−O

Answer: A) P−O6\frac{P - O}{6}6P−O

Rationale:

,The standard deviation in PERT is calculated as the difference between the

pessimistic time (P) and optimistic time (O) divided by 6.




4. Which of the following statements is TRUE about the float (slack) in a project

schedule?

A. Float is the time an activity can be delayed without delaying the project

completion.

B. Float is the time an activity can be delayed without affecting the critical path.

C. Float is always zero on the critical path.

D. Float is always positive on all activities.

Answer: C) Float is always zero on the critical path.

Rationale:

Activities on the critical path have zero float because any delay will directly impact

the project's overall completion time. Activities not on the critical path may have float

and can be delayed without affecting the project’s final duration.




5. What is the purpose of the forward pass in CPM scheduling?

A. To determine the project’s finish date.

B. To calculate the float for each activity.

, C. To calculate the latest start and finish times.

D. To determine the earliest start and finish times for each activity.

Answer: D) To determine the earliest start and finish times for each activity.

Rationale:

The forward pass is used to calculate the earliest possible start and finish times for

each activity based on the project’s start date and dependencies.




6. In the context of PERT and CPM, what does "float" or "slack" mean?

A. The difference between the early start and late start of an activity.

B. The total project time.

C. The difference between the early finish and late finish of an activity.

D. The duration of the critical path.

Answer: A) The difference between the early start and late start of an activity.

Rationale:

Float or slack refers to the amount of time an activity can be delayed without affecting

the project's completion time.




7. In a PERT network, if an activity has an optimistic time of 5 days, a most likely

time of 8 days, and a pessimistic time of 11 days, what is the variance of this activity?

Document information

Uploaded on
March 16, 2025
Number of pages
38
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers
$10.99

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
douglasmugwe82
5.0
(1)
Sold
2
Followers
0
Items
4217
Last sold
1 year ago



Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions