Written by students who passed Immediately available after payment Read online or as PDF Wrong document? Swap it for free 4.6 TrustPilot
logo-home
Exam (elaborations)

Contract Administration || with Accurate Answers 100%.

Rating
-
Sold
-
Pages
7
Grade
A+
Uploaded on
14-03-2025
Written in
2024/2025

On a new design and construction project, what is CPM best used for? correct answers identifying final delivery date of consultant drawings What is the primary purpose of a retainage (or holdback) on each progress payment to a contractor? correct answers To protect the owner against defective and incomplete work If it appears to the interior designer that the dollar amount requested on the contractor's application for payment exceeds the work completed and material stored, the designer should correct answers certify only the amount that the designer believes represents the work completed and stored, and attach a letter explaining why the amount certified differs from the amount applied for Which consultant is most likely to be responsible for designing the security systems on the majority of projects? correct answers Electrical Engineer When preparing bid documents, what can be included to allow the owner some flexibility in modifying the cost of the project when the bids are submitted? correct answers Alternative Does the the interior designer have the right to reject furniture and equipment? correct answers No only the owner does What three items are considered submittals? correct answers Shop drawings Samples Product data What are changes that don't affect a change in the cost or time schedule of a project. The interior designer is allowed to make minor changes in work without the owner's approval. correct answers Minor changes in work What is a change which must be made immediately but the owner and contractor can't agree on its cost and/or time revision. The purpose is to prevent construction delays, and usually results in an eventual change order? correct answers Construction change directive Document authorizing a change from the original contract documents which modifies the schedule, cost, or both. It is typically prepared by the interior designer but issued by the owner if the owner has the contractual agreement with the contractor? correct answers Formal change order General Conditions of the Contract for Construction (AIA Document A201) give the ________ __________ the authority to reject non-conforming construction work. correct answers interior designer

Show more Read less
Institution
Contract Administration
Course
Contract Administration

Content preview

Contract Administration || with Accurate Answers 100%.
On a new design and construction project, what is CPM best used for? correct answers
identifying final delivery date of consultant drawings

What is the primary purpose of a retainage (or holdback) on each progress payment to a
contractor? correct answers To protect the owner against defective and incomplete work

If it appears to the interior designer that the dollar amount requested on the contractor's
application for payment exceeds the work completed and material stored, the designer should
correct answers certify only the amount that the designer believes represents the work completed
and stored, and attach a letter explaining why the amount certified differs from the amount
applied for

Which consultant is most likely to be responsible for designing the security systems on the
majority of projects? correct answers Electrical Engineer

When preparing bid documents, what can be included to allow the owner some flexibility in
modifying the cost of the project when the bids are submitted? correct answers Alternative

Does the the interior designer have the right to reject furniture and equipment? correct answers
No only the owner does

What three items are considered submittals? correct answers Shop drawings
Samples
Product data

What are changes that don't affect a change in the cost or time schedule of a project. The interior
designer is allowed to make minor changes in work without the owner's approval. correct
answers Minor changes in work

What is a change which must be made immediately but the owner and contractor can't agree on
its cost and/or time revision. The purpose is to prevent construction delays, and usually results in
an eventual change order? correct answers Construction change directive

Document authorizing a change from the original contract documents which modifies the
schedule, cost, or both. It is typically prepared by the interior designer but issued by the owner if
the owner has the contractual agreement with the contractor? correct answers Formal change
order

General Conditions of the Contract for Construction (AIA Document A201) give the ________
__________ the authority to reject non-conforming construction work. correct answers interior
designer

, the General Conditions of the Contract for FF&E (AIA Document A251) does not give the
interior designer the right to reject items, as only the __________ has the power to reject. correct
answers Owner

How many days is the application for payment issued from the contractor to the interior
designer? correct answers 10

Once approved by the designer, _____% retainage is withheld until the completion of the entire
project. correct answers 10

Upon inspection and agreement, the interior designer issues a certificate of ______________
completion. correct answers substantial

What is a written or graphic document issued by the interior designer before the execution of the
contract that modifies or interprets the bidding documents by additions, deletions, clarifications,
or corrections. If this is done after the execution of the contract, it is called a bulletin? correct
answers An addendum

During the bidding process, you requested to hold an allowance for an art installation that would
be installed in the central lobby of a high rise condo building.
Now the building is in construction and you have made final selection of the artist and piece to
be installed. The final cost will be $1200 less than the original allowance.

This $1200 deduct will be logged in the project as which of the following? correct answers
Addendum
Change Directive
*Bulletin
Change Order

What would NOT be found in the project manual? correct answers Cost estimate

What is responsible for forwarding all warranties, manuals, certificates of inspection and bonds
during the project close-out phase? correct answers Contractor

What is a Tenant Work Letter? correct answers An agreement between the landlord and tenant
that details the initial tenant improvements (TI) to be built

Who is solely responsible for all fabrication, delivery, and installation means, methods,
techniques, and procedures, and for coordinating all portions of the work. correct answers
Contractor

What is a line item included in a budget to account for unknown conditions is called? correct
answers Contingency

Where are the requirements for how bidders should propose a substitution is found? correct
answers Instructions to bidders

Written for

Institution
Contract Administration
Course
Contract Administration

Document information

Uploaded on
March 14, 2025
Number of pages
7
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

$11.39
Get access to the full document:

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
SirAnton NURSING, ECONOMICS, MATHEMATICS, BIOLOGY, AND HISTORY MATERIALS BEST TUTORING, HOMEWORK HELP, EXAMS, TESTS, AND STUDY GUIDE MATERIALS WITH GUARANTEED A+ I am a dedicated medical practitioner with diverse knowledge in matters
View profile
Follow You need to be logged in order to follow users or courses
Sold
787
Member since
3 year
Number of followers
438
Documents
39533
Last sold
1 week ago
Reign Supreme Scholarly || Enlightened.

Get your revised study materials available here and elevate your educational outcomes. I have numerous verified learning materials (Research, Exams Questions and answers, Assignments, notes etc) for different courses guaranteed to boost your academic results. I am dedicated to offering you the best and unique learning content. You are encouraged to inquire further assistance from this end whenever need be. Kindly remember to leave your review, understanding your satisfaction is essential . We highly appreciate clients who always come back for more of the study content we offer, you are extremely valued. All the best.

Read more Read less
3.7

117 reviews

5
49
4
20
3
24
2
8
1
16

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions