100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached 4.2 TrustPilot
logo-home
Exam (elaborations)

NASCLA Exam 8

Rating
-
Sold
-
Pages
29
Grade
A+
Uploaded on
11-03-2025
Written in
2024/2025

Exam of 29 pages for the course nascla at nascla (NASCLA Exam 8)

Institution
Nascla
Course
Nascla










Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Institution
Nascla
Course
Nascla

Document information

Uploaded on
March 11, 2025
Number of pages
29
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers

Content preview

1. What is the first step in the construction project management
process?
• A) Assigning workers to tasks
• B) Securing financing
• C) Defining project scope and goals
• D) Signing contracts with subcontractors
• Answer: C) Defining project scope and goals
• Rationale: Clearly defining the scope, objectives, and
deliverables of the project is the first step in construction project
management.


2. What is the purpose of a performance bond in construction?
• A) To guarantee payment for workers
• B) To ensure subcontractors are paid on time
• C) To ensure that the project will be completed as per the
contract
• D) To secure insurance coverage for workers
• Answer: C) To ensure that the project will be completed as
per the contract

,• Rationale: A performance bond guarantees that the
contractor will complete the project in accordance with the
contract terms.


3. Which of the following is an essential characteristic of a
contract's "indemnification clause"?
• A) It ensures the client is compensated for any delays
• B) It prevents the contractor from modifying the project
scope
• C) It requires one party to compensate the other for damages
or losses
• D) It sets the timeline for project completion
• Answer: C) It requires one party to compensate the other for
damages or losses
• Rationale: An indemnification clause typically holds one
party financially responsible for damages, losses, or legal fees
incurred by the other party.


4. What is typically required from a contractor when applying for
a building permit?
• A) Detailed blueprints and proof of financing
• B) The project’s timeline and the contractor's resume
• C) Proof of insurance and bonding
• D) None of the above

, • Answer: A) Detailed blueprints and proof of financing
• Rationale: To obtain a building permit, contractors usually
need to submit detailed blueprints for the project and proof of
financing to ensure the project complies with regulations.


5. When is a contractor required to apply for a building permit?
• A) When the project exceeds $50,000 in cost
• B) When the project involves changes to the structure or
systems of a building
• C) Before any work begins
• D) Only if the work requires special permits, like electrical
or plumbing work
• Answer: B) When the project involves changes to the
structure or systems of a building
• Rationale: Building permits are generally required for work
that alters the structure or systems (electrical, plumbing, etc.) of a
building.


6. What is a lien in the context of construction projects?
• A) A form of insurance for workers
• B) A claim placed on property for unpaid work or materials
• C) A tax paid to the government
• D) A bond securing payment to contractors
$9.49
Get access to the full document:

100% satisfaction guarantee
Immediately available after payment
Both online and in PDF
No strings attached

Get to know the seller
Seller avatar
douglasmugwe82
5.0
(1)

Get to know the seller

Seller avatar
douglasmugwe82 Teachme2-tutor
View profile
Follow You need to be logged in order to follow users or courses
Sold
2
Member since
1 year
Number of followers
0
Documents
4239
Last sold
2 months ago
fully answered questions and answer

fully answered questions and answer

5.0

1 reviews

5
1
4
0
3
0
2
0
1
0

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions