The maximum size of the conduit or pipe shall NOT exceed _______ of the thickness of the
concrete. - Correct Answer 1/3"
"Which of the following tests for concrete is conducted at the site/field? - Correct Answer
Color Test
Explanation:
Rest of the above are laboratory tests."
"Which of the following factor influence the positioning of the joints in a slab on grade? -
Correct Answer ALL OF THESE
-Sub grade conditions
-Finishing requirements
-Temperature"
"Which of the following is NOT a property of concrete? - Correct Answer High tensile
strength"
"The concrete work is done in freezing zones, it gets cured by ______________. - Correct
Answer Steam
Explanation:
It is done by heating concrete by steam or using alternating current, so that water content in
the concrete is not increased."
"What type of aggregate is formed by crushing, sizing, screening an existing hardened
concrete surface or structure? - Correct Answer Recycled aggregate"
"The concrete paving operations includes: - Correct Answer ALL OF THESE!
, -Preparation of sub grade
-Specified equipment
-Construction of joints"
"If the concrete compressive strength specified is less than 3600 psi, it has the option of
being tested at 28 days and is able to accept the concrete if it attains ___________
percentage of the minimum required strength. - Correct Answer 85"
"If the admixtures are used in concrete for the purpose of delayed setting and hardening of
concrete, they are called _____________? - Correct Answer Retarders"
"Which of the following are the general types of vibrating needles that are in use? - Correct
Answer ALL ANSWERS!
-Internal vibrators
-Immersion vibrators
-Surface vibrators"
"Concrete proportioning is done based on the facilities available at the site. Which are the
general proportioning methods used for concrete? - Correct Answer ALL OF THESE
-Surface area method
-Mix design based on flexural strength
-Maximum destiny method"
"The minimum cementitious material that is required for concrete bridging deck is
______________lbs/cu yd. - Correct Answer 675"
"The amount of free water used in concrete shall not exceed ____________ pounds per cubic
yard of concrete. - Correct Answer 310
Explanation:
If the SCM are added, it can be increased to 20 pounds per each required 100 pounds of
cementitious material in excess of 550 pounds per cubic yard."