and Answers 100% Pass
Grant Assurance #29, Airport Layout Plan - ✔✔Airport sponsors must keep the ALP
updated at all times. Must be FAA approved.
5 Primary functions of the ALP - ✔✔-Necessary to receive AIP funding
-Blueprint for Airport Development
Public Document that serves asa record of aeronautical requirements
-Enables FAA and Airport Sponsor to plan for improvements
-Working tool for airport staff.
The ALP does not - ✔✔-Release any Federal Obligations
-Does not constitute FAA approval to use land for non-aeronautical purposes.
How often should the ALP be reviewed? - ✔✔2-7 years
Grant assurances require airport management to keep the following items up to date. -
✔✔-Property Lines
100% Pass Guarantee Katelyn Whitman, All Rights Reserved © 2025 1
,-Location and nature of all existing and proposed facilities and structures.
-Location of all existing and proposed non-avitaion areas.
Safe - ✔✔meets design standards or modified design standards and provides for safe
operation of aircraft
Useful - ✔✔airport is making the best use of airport land while minimizing the impact
of off-airport structures.
Efficient - ✔✔planned capacity is sufficient for forecast demand
Airport Master Record (FAA 5010) - ✔✔Used to update the AF/D/Chart Supplement
NPIAS report identifies: - ✔✔Public airport included in the NPIAS, their role, and
amount and types of airport development eligible for federal funding under the AIP
over the next 5 years.
****FAA Believes the Airport Should BE**** - ✔✔-Safe and efficient-maintained to
design standards
-Affordable-rely on user fees (self sufficient)
-Flexible & Expandable-accommodate new aircraft types
-Permanent-assurance they will remain open
-Maintain a balance-between the community & ATC
100% Pass Guarantee Katelyn Whitman, All Rights Reserved © 2025 2
, -Support National Objectives-including national defense, natural disasters
-Extensive-no more than 20 miles to next NPIAS airport.
State and Metropolitan./Regional Airport System Planning - ✔✔recommends the
general characteristics and location of new airports and nature of development and
expansion of existing airports.
Elements of State Aviation System Plan - ✔✔-System needs identification
-System-wide development cost estimate
-Determine and prioritize aeronautical needs
-Meet any relevant state standards
Master Plan - ✔✔a comprehensive study of an airport and usually describes the short,
medium, and long-term development plans to meet future demand. Out to 20 years.
Sequenced into the Airport Capital Improvement Plan as a project eligible for Federal
Funding.
Products of a Master Plan - ✔✔-Technical Report
-Summary Report
-ALP
-Web Page
100% Pass Guarantee Katelyn Whitman, All Rights Reserved © 2025 3