questions with verified answers
Gathering and documenting the lessons learned is completed as part of the
_______ phase of the project life cycle.
a. planning
b. defining
c. executing
d. closing Ans✓✓✓-d. closing
The project manager is responsible for documenting and gathering the lessons
learned during the closing phase of the project.
How do the phases of iteration differ from the phases of the project life cycle?
a, The phases are sequential.
b. The phases are not dependent upon each other.
c. Each phase is a project with a deliverable. Ans✓✓✓-C. While the phases of the
project life cycle form the parts of a whole project, each phase of the iteration
cycle is its own project with a deliverable.
In the project executing phase, what are major areas for monitoring?
a. Cost, schedule, and scope
, b. Project justification
c. Sponsor requirements Ans✓✓✓-a. cost, schedule, scope
These are the major areas that are monitored during the project executing phase.
Major project outcomes and deliverables, how the project will be completed, and
a high-level estimate of the cost and completion time are included in the _____.
a. project concept document
b. project proposal
c. project charter Ans✓✓✓-b. project proposal
Major project outcomes and deliverables, how the project will be completed, and
a high-level estimate of the cost and completion time are included in the project
proposal.
The approval of the scope, budget, and schedule mark the end of the _______
phase of the project life cycle.
a. planning
b. defining
c. closing
d. executing Ans✓✓✓-a. planning
The planning phase creates an approved scope, budget, and schedule so that the
project can move to the executing phase of the project life cycle.
The end of the defining phase is marked by the approval of the _______.
a. project plan
b. scope statement