Stockpiles of aggregate shall be
maintained in a well-drained
condition in order to:
ANSWER-Minimize Free Water
Content
Coarse aggregate stockpiles
must be sprinkled for at least
,how many hours prior to batch
for FDOT?
ANSWER-24
Free moisture of the aggregate
means:
ANSWER-Moister on the
surface of an aggregate that is
above and beyond the
absorbed moister in the
aggregate.
, If the moister test is done other
than by the cook-out method,
how often shall the other
methods be verified?
ANSWER-Each week
For drill shaft concrete, the
quantity of cement replaced
with fly ash shall be:
REAL EXAM WITH COMPLETE DETAILED QUESTIONS AND
CORRECT VERIFIED ANSWERS ALREADY GRADED A+
Stockpiles of aggregate shall be
maintained in a well-drained
condition in order to:
ANSWER-Minimize Free Water
Content
Coarse aggregate stockpiles
must be sprinkled for at least
,how many hours prior to batch
for FDOT?
ANSWER-24
Free moisture of the aggregate
means:
ANSWER-Moister on the
surface of an aggregate that is
above and beyond the
absorbed moister in the
aggregate.
, If the moister test is done other
than by the cook-out method,
how often shall the other
methods be verified?
ANSWER-Each week
For drill shaft concrete, the
quantity of cement replaced
with fly ash shall be: