Questions with Correct Answers
What is the contractor's Quality Control plan? - Answer-Framework for contractor's
process for delivering quality within plans and specifications.
Who do you submit the QC plan to in accordance with spec? - Answer-to the Engineer
What materials are not under the QCP? - Answer-Not sod and sealer
What is the contractor's responsibility of the QC Plan? - Answer-Submit is to the
departments database for Engineer approval.
When can you revise the QC plan? - Answer-5 days prior to implementation of changes.
The QC program is what? - Answer-The contractor's QC plan and the Producer's QC
Program for that project
The Contractor's QC plan is limited to what? - Answer-Just that project
The Producers QC Program is submitted to the DMO for acceptance of what? - Answer-
Hot Mix Asphalt
Portland Cement Concrete (Structural)
Earthwork
Timber
Prestressed and/or Precast Concrete Products
Drainage Products
The Producers QC Program is used where? - Answer-Acceptance is Statewide
Portland Cement Concrete shall meet the requirements of - Answer-Section 9.2 Volume
II of the Department's Materials Manual
Producers QC Program is based on what - Answer-Section 105
The Department will accept or reject the QC plan within how many days? - Answer-10
Days
, The QC Manager must be onsite or available within - Answer-Four hours notice
QC related reports and documentation must be maintained for a period of - Answer-3
years
Can a contractor have an approved QC plan without having a contract with the
Department? - Answer-No it is contract specific
What is a contractor submits a supplier's name who is not on the approved list? -
Answer-Operations will be suspended until ammended
Does the contractor have to submit a QC plan for each contract? - Answer-Yes and No
Only if QC materials are required
Who does a producer submit a QC Program to? - Answer-SMO or DMO
Statewide Acceptance
Who does the contractor submit the QC plan to? - Answer-The Engineer
What role does the DMO play in approving the contractor's QC plan? - Answer-Review
the material availability on mix design to certify that that material is readily available.
What are Raw Material vs Final Product - Answer-Raw Materials make up the final
product
Who qualifies technicians? - Answer-CTQP through providers
When can a company work for a contractor and FDOT? - Answer-Submit proposed
Consultant certifying that no conflict of interest 8-5
Resolution Labs must be accredited with? - Answer-AASHTO
If any part of the CQP is suspended the contractor bears all - Answer-Delay costs and
there will be No change in contract time or completion dates
What three entities performs Quality Control? - Answer-Manufacturer
Producer
Contractor
What entity performs Quality Assurance? - Answer-FDOT
POSCVRM stands for - Answer-Plan
Organize
Staff
Check
Verify