Bulk Specific Gravity formula - ....ANSWER...dry /
SSD - water weight = BSG
Asphalt Temperature Heat and Cold -
....ANSWER...Too hot cooks asphalt
Too cold can't compact
The hole for temping asphalt trucks should be located
where - ....ANSWER...Hole located in the middle third of
length of truck; 6-10 inches above the bed
Temping asphalt on the top - ....ANSWER...At
engineer's discretion
Asphalt Temperature Master Range - ....ANSWER...+-
1
,30; reject loads outside
Temp every load monitored if - ....ANSWER...Mix
within master range
Differes for a single load from established temp by
+-25°F
Avg of five loads differes by +-15°F
Monitor until within tolerance
2
, Tack Distributor without a calibration chart -
....ANSWER...If they don't have a calibration chart you
can not use them to distribute tack
Application rate of tack for close graded mixes -
....ANSWER...Normal: 0.02-0.08 gal/yd^2 Must
apply temperature correction factor
After placing the simple level on the pavement then you
- ....ANSWER...Raise the down end of the level until it
is level (bubble center)
After the simple level is lifted until it is level you
measure what - ....ANSWER...The length of the simple
level and the height between the (previously down) end
of the level to the pavement
Formula to calculate the manual cross slope -
....ANSWER...Calculate the slope using the formula (
h / l ) x 100 = slope %
Requirements for the rolling Straightedge -
3
WELL RESEARCHED EXAM
QUESTIONS WITH 100% DETAILED
VERIFIED AND CORRECT
ANSWERS ACTUAL BRAND-NEW
EXAM ALREADY GRADED A+
Bulk Specific Gravity formula - ....ANSWER...dry /
SSD - water weight = BSG
Asphalt Temperature Heat and Cold -
....ANSWER...Too hot cooks asphalt
Too cold can't compact
The hole for temping asphalt trucks should be located
where - ....ANSWER...Hole located in the middle third of
length of truck; 6-10 inches above the bed
Temping asphalt on the top - ....ANSWER...At
engineer's discretion
Asphalt Temperature Master Range - ....ANSWER...+-
1
,30; reject loads outside
Temp every load monitored if - ....ANSWER...Mix
within master range
Differes for a single load from established temp by
+-25°F
Avg of five loads differes by +-15°F
Monitor until within tolerance
2
, Tack Distributor without a calibration chart -
....ANSWER...If they don't have a calibration chart you
can not use them to distribute tack
Application rate of tack for close graded mixes -
....ANSWER...Normal: 0.02-0.08 gal/yd^2 Must
apply temperature correction factor
After placing the simple level on the pavement then you
- ....ANSWER...Raise the down end of the level until it
is level (bubble center)
After the simple level is lifted until it is level you
measure what - ....ANSWER...The length of the simple
level and the height between the (previously down) end
of the level to the pavement
Formula to calculate the manual cross slope -
....ANSWER...Calculate the slope using the formula (
h / l ) x 100 = slope %
Requirements for the rolling Straightedge -
3