Dau Clc 206, Cor In A Contingency
Environment Questions And Answers
100% Correct!!!
As a COR in a contingency setting, you are responsible for conducting safety
inspections of all facilities on post. During today's inspection, you observe that
locks are installed on the exterior doors of the workers' dormitory. What
should you do?
Answer: Notify the Contracting Office about the observation; the KO
should inform the Commander.
Which of the following is considered a prohibited gift?
Answer: A gift of appreciation from a new contractor.
In a contingency environment, the need for vigilance is reduced. Is this true or
false?
Answer: False
While working in an OCONUS contingency environment, a lack of
understanding of local communication methods can lead to contract failure. Is
this statement true or false?
Answer: True
Which form is not acceptable for receipt by the COR?
Answer: DD Form 254
An organizational conflict of interest occurs when you have a financial stake
in a contract or a matter that affects the contractor in which of the following
situations?
Answer: All of the provided answers are correct.
A contingency contract is only used in military operations or during hostilities
with a foreign enemy or opposing force. Is this true or false?
Answer: False
Environment Questions And Answers
100% Correct!!!
As a COR in a contingency setting, you are responsible for conducting safety
inspections of all facilities on post. During today's inspection, you observe that
locks are installed on the exterior doors of the workers' dormitory. What
should you do?
Answer: Notify the Contracting Office about the observation; the KO
should inform the Commander.
Which of the following is considered a prohibited gift?
Answer: A gift of appreciation from a new contractor.
In a contingency environment, the need for vigilance is reduced. Is this true or
false?
Answer: False
While working in an OCONUS contingency environment, a lack of
understanding of local communication methods can lead to contract failure. Is
this statement true or false?
Answer: True
Which form is not acceptable for receipt by the COR?
Answer: DD Form 254
An organizational conflict of interest occurs when you have a financial stake
in a contract or a matter that affects the contractor in which of the following
situations?
Answer: All of the provided answers are correct.
A contingency contract is only used in military operations or during hostilities
with a foreign enemy or opposing force. Is this true or false?
Answer: False