After safety concerns have been addressed and the initial water source has been stopped, the
restorer must complete an evaluation of the water's migration through the structure. During this
process, the restorer inspects all ___________ ________ areas. potentially affected
the ultimate goal is to find the edge of water migration which moves in a three dimensional path
throughout the structure. this is accomplished across carpeted surfaces using a _____ and across
most hard surfaces using a _____ (non-penetrating) moisture meter. moisture sensor , non-
invasive
water from a clean source with no substantial risk of causing sickness or discomfort is said to be
category 1
water that has significant degree of chemical biological and or physical contamination and
potential to cause sickness or discomfort is ___________ category 2
cleaning procedures must be employed before the drying of a category 2 water loss can continue.
at a minimum affected __________ must be removed and disposed of and carpet must be
throughly cleaned using a hot water extraction method. carpet underlay
When water intrusion results from a grossly unsanitary source or carries __________ (disease
causing) agents, it is said to be Category 3. pathogenic
,worker and occupant ______ and safety are the 1st priority on every sewage loss. areas affected
by category 3 water intrusion are marked and posted as potentially hazardous. health
Various cleaning and decontamination procedures must be used on Category 3 water losses,
including the removal of all ______ ______ materials affected by the water intrusion.
highly porous
when resistance is encountered and performing proper services in a category 3 water loss
becomes a challenge restorers _____________ immediately to prevent liability and address the
conflict. stop work
Third party experts are commonly referred to as Indoor Environmental Professionals, or ____.
IEP
Losses where regulated or hazardous materials have contaminated the structure do not change
the _______ of water. category
pre-existing conditions should be identified documented and communicated to all _________
parties during the initial inspection. materially interested
when carpet delimitation (the loss of integrity in the adhesives used to laminate the _____ and
_____ backings) has occurred, further damage is very likely. for this reason when extensive
carpet delimitation is discovered technicians must call it to the attention go all materially
interested parties , document the condition and suggest replacement. primary and
secondary
, there are number of causes for carpet delimitation - many of them relates to ____ restoration
activities improper
Many building materials will absorb excess water vapor and suffer damage, especially when air
is allowed to remain above __% relative humidity. 60%
Hygroscopic materials gain and lose moisture continually in an effort to ________ with the water
content in the surrounding air mass. The more hygroscopic the material, the faster it will collect
water vapor, and the easier it will suffer _________ damage. equalize and secondary
When water intrusion results in water running through wall cavities, inspection access holes are
used to ensure that blown-in insulation has not compacted and lost its ______. Wet compressed
insulation should be ______ R-Value , removed
the most effective way to speed the drying process is to remove as much of the water in a liquid
state as possible during the _____ phase (for example multiple extractions.) poor extractions will
significant slow the drying process. extractions
Abide by local ____ and regulations when disposing extracted water. Waste water is best
disposed of into a sanitary sewer. laws
the primary goal of the initial extraction of the affected area is to contain further ______ of the
water within the structure. migration