Which of these is a contract Document:
1. Standard Specifications
2. Basis of Estimates (BOE) Manual
3. Construction Project Administration Manual (CPAM) 1. Standard Specifications
Monthly payments are based on: A Contractor's Monthly Estimate
Once the contract is executed, the only way to modify the contract document is through:
1. Supplemental Agreements (SA)
2. Work Orders (WO)
3. Unilateral Payment
How are work order funds encumbered? Through contingency Supplemental Agreements
(CSA)
When are unilateral payments used? When the department and contractor cannot agree on
the terms or the contractor fails to timely execute: a work order or supplemental agreement
What is the governing order of contract documents? 1. Special Provisions
2. Technical Special Provisions
3. Plans