Final Exam Review OPMA 3306
questions with 100% complete solutions
A BOM file is also called which of the following - correct answer ✔✔Product Tree
MRP stands for Material Requirements Planning - correct answer ✔✔True
A project can be subdivided into which of the following - correct answer ✔✔work
packages
MRP is most valuable where a number of products are made in batches using the
same productive equipment - correct answer ✔✔True
PERT is an abbreviation for which of the following methodologies - correct answer
✔✔Program Evaluation and Review Technique
How many free trade zones are there in the US - correct answer ✔✔about 260
A master production schedule is an input to a material requirements planning
(MRP) system - correct answer ✔✔True
An input to the material requirements planning (MRP) system is an exception
report - correct answer ✔✔False
, Which of the following are eligible companies to be considered for the Baldrige
award - correct answer ✔✔auditing firms
An input to the material requirements planning (MRP) system is an inventory
records file - correct answer ✔✔True
MRP systems seek to achieve - correct answer ✔✔determine the number of
dependent demand items needed
A modular bill of materials includes items with fractional options - correct answer
✔✔False
An analytical tool used in six-sigma quality improvement programs is which of the
following - correct answer ✔✔checksheets
In monitoring process quality we might use which of the following statistics -
correct answer ✔✔difference between the highest and lowest value in a sample
Quality of life in a host community is not a major factor in making the facility
location decision - correct answer ✔✔False
AQL stands for accepting questionable lots in production quality management -
correct answer ✔✔False
Net change MRP systems are "activity" driven - correct answer ✔✔True
A BOM file is also called - correct answer ✔✔Product Tree
questions with 100% complete solutions
A BOM file is also called which of the following - correct answer ✔✔Product Tree
MRP stands for Material Requirements Planning - correct answer ✔✔True
A project can be subdivided into which of the following - correct answer ✔✔work
packages
MRP is most valuable where a number of products are made in batches using the
same productive equipment - correct answer ✔✔True
PERT is an abbreviation for which of the following methodologies - correct answer
✔✔Program Evaluation and Review Technique
How many free trade zones are there in the US - correct answer ✔✔about 260
A master production schedule is an input to a material requirements planning
(MRP) system - correct answer ✔✔True
An input to the material requirements planning (MRP) system is an exception
report - correct answer ✔✔False
, Which of the following are eligible companies to be considered for the Baldrige
award - correct answer ✔✔auditing firms
An input to the material requirements planning (MRP) system is an inventory
records file - correct answer ✔✔True
MRP systems seek to achieve - correct answer ✔✔determine the number of
dependent demand items needed
A modular bill of materials includes items with fractional options - correct answer
✔✔False
An analytical tool used in six-sigma quality improvement programs is which of the
following - correct answer ✔✔checksheets
In monitoring process quality we might use which of the following statistics -
correct answer ✔✔difference between the highest and lowest value in a sample
Quality of life in a host community is not a major factor in making the facility
location decision - correct answer ✔✔False
AQL stands for accepting questionable lots in production quality management -
correct answer ✔✔False
Net change MRP systems are "activity" driven - correct answer ✔✔True
A BOM file is also called - correct answer ✔✔Product Tree