What is the maximum horizontal spacing for support of 3/4" CPVC pipe? - CORRECT ANSWER 3'
What does ASHRAE stand for? - CORRECT ANSWER American Society of Heating, Refrigeration and Air
Conditioning Engineers (Ref. Standards)
What is the 4th of the seven basic steps for special inspections? - CORRECT ANSWER Prescribe on-site
and final report requirements and give the requirements to the agencies.
Drainage tiles shall be placed on a minimum of ________ inches of washed gravel or crushed rock. -
CORRECT ANSWER 2
Particleboard shall conform to _______________ and shall be so identified by a grade mark or certificate
of inspection by an approved agency - CORRECT ANSWER ANSI A-208.1
What is the maximum stud spacing for Diagonal Wood Bracing (DWB)? - CORRECT ANSWER 24"
What is the minimum length of a Diagonal Wood Braced wall panel on a 9' wall? - CORRECT ANSWER
48"
Of the following, which is not a responsibility of the building official regarding in special inspections:
a. Review the submittal documents
b. Approve the materials
c. Check on previous jobs done by this special inspector
d. Approve of the special inspector program - CORRECT ANSWER c. Check on previous jobs done by this
special inspector