Constructability reviews - CORRECT ANSWER - reviewing the design (and drawings) to
identify problems that might me the project difficult/impossible to construct
asking the questions "Will this impact the cost, time, or quality of the project?" and "Will the
contractor, or subcontractors, require an answer to this question in order to perform their work?"
So from that it seems that it should also be looking for gaps in the documents.
differences between contingency for design vs contingency for the entire project vs contingency
held by the contractor. Also look at when design fees are percentage of construction cost based
how they are (or aren't) affected by contingency. - CORRECT ANSWER -
1 yd = - CORRECT ANSWER - 3 ft
1 yd2 - CORRECT ANSWER - 9 ft2
1 yd3 - CORRECT ANSWER - 27 ft3
1 acre = ? square feet - CORRECT ANSWER - 43,560 square feet
1 acre = - CORRECT ANSWER - 4840 yards
Bid requirements - CORRECT ANSWER - Bid solicitation
Instructrions to bidders
Info available to bidders
Bid forms and supplements
, Contract forms - CORRECT ANSWER - Agreement
Performance bond
Payment bond
Certificate
Conditions of the contract - CORRECT ANSWER - General
Supplementary
Specifications - CORRECT ANSWER - Div 1. Gral requirements
Div 2. Site construction
Div 3. Concrete
Div 4. Masonry
Div 5. Metals
Div 6. Wood & plastics
Div 7. Thermal & moisture protection
Div 8. Doors and windows
Div 9. Finishes
Div 10. Specialties
Div 11. Equipment
Div 12. Furnishings
Div 13. Special construction
Div 14. Conveying systems
Div 15. Mechanical
Div 16. Electrical
What is included in the project manual - CORRECT ANSWER - Bidding requirements
Contract forms
Conditions of the contract