questions with verified answers
True or False: In most instances, the EPCM model is structured based on a cost-
reimbursable fee structure or a unit rate fee structure. Ans✓✓-True
Which stage in AWP is when you turn over the project and do project closeout?
Ans✓✓-Stage 5
All change orders must be approved by who/whom? Ans✓✓-The owner and
contractor, both must agree
In construction, a change order refers to the documentation of an agreement to
do what following tasks, select all that apply Ans✓✓-deviate from the original
scope; add work; subtract work; alter the design
True or False: Proper change order management enables teams to mitigate
significant costs and schedule disruptions in construction. Ans✓✓-True
The procurement plan must be aligned with your what two areas. Select the two
that are correct. Ans✓✓-engineering design basis and construction strategy
EPCM contractor is responsible for establishing contractual agreements on behalf
of the owner or principal with other parties, select all that apply Ans✓✓-vendors;
sub-contractors; other contractors; vendors of sub-contractors
, For large-scale, critical infrastructure projects, an EPC contract provides a highly
effective _____________. Ans✓✓-turnkey solution
True or False: EPCM stands for engineering, procurement, and construction
management. Ans✓✓-true
True or False: At its core, change order is work that is added or removed from the
original contractor's scope of work, as agreed upon in the contract signed by the
client and contractor before work began. Ans✓✓-true
True or False: Advanced work packaging is an industry best practice
(methodology) that focuses on proper & thorough front-end planning, along with
the alignment of EPCM activities and deliverables, to achieve improved project
performance. Ans✓✓-true
EPC contracts are an all-encompassing what type of contract? Ans✓✓-lump sum
True or False: The document control system in the AWP method will have your
schedule, purchase orders, and requisitions. Ans✓✓-true
All change orders need to include detailed information, including __________.
Select all that apply Ans✓✓-a summary by the contractor of the total cost of the
proposed change; a description of the requested change compared to the original
contract or bid; itemized documentation of any subcontractor costs; a statement
of the contractual basis for the requested change and its impact on the project
completion date
True or False: The journal of construction engineering explains, " various reasons
for construction cost and schedule overruns in any project include design error,