L4M5 Exam Study Guide.
Procurement staff may be required to negotiate not just with suppliers but also with -
Answer✔internal users, budget holders, contract managers and a multiplicity of other internal
and external stakeholders
Stakeholders - Answer✔From a negotiation perspective, stakeholders can be defined as persons
or groups that have an interest (or stake) in the outcome of the negotiation you are leading or
participating in
Negotiation is an expected core skill that involves - Answer✔considerations of approach,
objectives and people and power aspects
There is typically a cost associated with the negotiation process, so the buyer must consider -
Answer✔the cost-benefit analysis of negotiation
Various costs of the negotiation can include - Answer✔Time in preperation, analysis, senior staff
time and facilitation costs
Negotiation can begin from - Answer✔the first communication between buyer and supplier right
through to the final signing of the contract, mobilisation, contract management and contract exit
1|Page
, ©EVERLY 2024/2025 ALL RIGHTS RESERVED.
It is the buyers responsibility to - Answer✔negotiate best terms, conditions and price for every
purchase whilst maintaining quality of service as well as a productive working relationship with
their suppliers
Negotiation is defined as - Answer✔A process through which parties move from their initially
divergent positions to a point where agreement may be reached
Negotiation - Content - Answer✔- What you are negotiating about
- Unique to each negotiation
Negotiation - Process - Answer✔- How the negotiation is managed
- Generic stages all negotiations go through
The CIPS Procurement and Supply Cycle - Answer✔1. Define Business needs and develop
specification
2. Market analysis/make or buy decision
3. Develop the strategy and plan
4. Pre-procurement market testing
5. Develop documentation and detailed specification
6. Supplier selection to participate in tender
7. Issue tender documents
8. Bid and tender evaluation and validation
9. Contract award and implementation
2|Page
, ©EVERLY 2024/2025 ALL RIGHTS RESERVED.
10. Warehouse, logistics and receipt
11. Contract performance and improvement
12. Supplier relationship management
13. Asset management
Where negotiation situations typically arise in the procurement cycle - Step 1. Define Business
needs and develop specification - Answer✔The greatest opprtunity for cost reduction is at the
design stage. Negotiation with the budget holder is needed regarding the target price. Perhaps
their budget is not realistic for the quality or performance requirements needed in the market?
Where negotiation situations typically arise in the procurement cycle - Step 2. Market
analysis/make or buy decision - Answer✔Evaluation of bargaining power between the buyer and
different suppliers will help with analysis of the market to suggest whether it would be sensile to
focus on smaller suppliers where leverage may be greater, or larger due to the likelihood for
failure of the smaller.
Where negotiation situations typically arise in the procurement cycle - Step 3. Develop the
strategy and plan - Answer✔This step is where the decision regarding whether and what to
negotiate is made.
Where negotiation situations typically arise in the procurement cycle - Step 4. Pre-procurement
market testing - Answer✔This step is where supplier conditioning can begin. Meeting suppliers
can attract more interest in your business or reveal your business as not as attractive as you
thought, necessitating a change in strategy. Early supplier conditioning eg focusing on a specific
3|Page
, ©EVERLY 2024/2025 ALL RIGHTS RESERVED.
factor such as quality or cost can also put in suppliers minds the need to focue on these areas in
their bids
Where negotiation situations typically arise in the procurement cycle - Step 5. Develop
documentation and detailed specification - Answer✔There is typically limited commerical
negotiation activity here, especially in public sector procurement
Where negotiation situations typically arise in the procurement cycle - Step 6. Supplier selection
to participate in tender - Answer✔There is typically limited commerical negotiation activity here
Where negotiation situations typically arise in the procurement cycle - Step 7. Issue tender
documents - Answer✔There is typically limited commerical negotiation activity here. This stage
normally follows on automatically from the preceding stage and is driven from the results of the
evaluation of initial bids with the highest scoring bidders invited to submit a formal priced bid
which may or may not be followed by negotiation
Where negotiation situations typically arise in the procurement cycle - Step 8. Bid and tender
evaluation and validation - Answer✔This is the first stage where detailed commercial
negotiation may start. The buyer has received the tender/bids or quotes from potential supploer
so has an opening position from competing bidders from which negotiations may begin
Where negotiation situations typically arise in the procurement cycle - Step 9. Contract award
and implementation - Answer✔At this stage the buying organisation has decided on the suppliers
they want, but there may be an opportunity to negotiate further concessions before informing
them and awarding the contract, as the supplier is not aware the decision has already been made.
4|Page