t/f; general conditions are modified by division
01 - general requirements, in the specifications
- ANSWER-false
,Bidding Requirements covered in Division 01 -
General Requirements include all but which of
the following?
a. Substitution procedures
b. Alternate bid descriptions
c. Bid bond
d. Owner-furnished/Contractor-installed (OFCI)
products - ANSWER-c. Bid bond
Which of the following is untrue regarding
Division 01 - General Requirements?
a. Contains project-specific administrative
requirements.
b. Specifies administrative and procedural
requirements for administering provisions in the
General Conditions of the Contract.
c. Division 01 - General Requirements modify
the General Conditions.
d. Division 01 - General Requirements is an
inherent part of the Specifications. - ANSWER-
c. Division 01 - General Requirements modify
the General Conditions
, t/f; division 01 general requirements and the
drawings should be coordinated - ANSWER-
true
t/f; division 01 general requirements
specifications are written in 3 part section
format similar to sections in divisions 02 - 49 -
ANSWER-true
t/f; facility commissioning requirements are
included in division 01 general requirements -
ANSWER-true
t/f; the architect/engineer is a signer of the
owner contractor agreement - ANSWER-false
t/f; general conditions are commonly produced
by professional associations - ANSWER-true
t/f; general conditions produced by professional
associations rarely require modifications -
ANSWER-False
EXAM LATEST
2024/2025 WITH
QUESTIONS AND
CORRECT ANSWRS
GRADED A+
GUARANTEED
PASS
t/f; general conditions are modified by division
01 - general requirements, in the specifications
- ANSWER-false
,Bidding Requirements covered in Division 01 -
General Requirements include all but which of
the following?
a. Substitution procedures
b. Alternate bid descriptions
c. Bid bond
d. Owner-furnished/Contractor-installed (OFCI)
products - ANSWER-c. Bid bond
Which of the following is untrue regarding
Division 01 - General Requirements?
a. Contains project-specific administrative
requirements.
b. Specifies administrative and procedural
requirements for administering provisions in the
General Conditions of the Contract.
c. Division 01 - General Requirements modify
the General Conditions.
d. Division 01 - General Requirements is an
inherent part of the Specifications. - ANSWER-
c. Division 01 - General Requirements modify
the General Conditions
, t/f; division 01 general requirements and the
drawings should be coordinated - ANSWER-
true
t/f; division 01 general requirements
specifications are written in 3 part section
format similar to sections in divisions 02 - 49 -
ANSWER-true
t/f; facility commissioning requirements are
included in division 01 general requirements -
ANSWER-true
t/f; the architect/engineer is a signer of the
owner contractor agreement - ANSWER-false
t/f; general conditions are commonly produced
by professional associations - ANSWER-true
t/f; general conditions produced by professional
associations rarely require modifications -
ANSWER-False