How many project management knowledge areas are there in the PMBOK 6th Edition? - correct answer10 project management knowledge areas
How many project management processes are covered in the PMBOK 6th Edition? - correct answer49 project management processes
What are the 10 project management knowledge areas? - correct answerCommunications Management
Cost Management
Integration Management
Quality Management
Procurement Management
Resource Management
Risk Management
Schedule Management
Scope Management
Stakeholder Management
What are the 5 project management domains? - correct answerInitiating (8 tasks)
Planning (13 tasks)
Executing (7 tasks)
Monitoring (7 tasks)
Closing (7 tasks)
What are the 8 tasks involved in initiating a project? - correct answer1. Assess the project
2. Key deliverables
3. Stakeholder analysis
4. Risks & constraints
5. Project charter
6. Approval of project charter by sponsor
7. Benefit analysis
8. Inform stakeholders
Initiating: Task 1 - correct answerPerform project assessment based upon available information, lessons learned from previous projects, and meetings with relevant stakeholders in order to support the evaluation of the feasibility of new products or services within the given assumptions and/or constraints.
Initiating: Task 2 - correct answerIdentify key deliverables based on the business requirements in order to manage customer expectations and direct the achievement of project goals.
Initiating: Task 3 - correct answerPerform stakeholder analysis using appropriate tools and techniques in order to align expectations and gain support for the project
Initiating: Task 4 - correct answerIdentify high level risks, assumptions, and constraints based on the current environment, organizational factors, historical data, and expert judgement, in order to propose an implementation strategy.
Initiating: Task 5 - correct answerParticipate in the development of the project charter by compiling and analyzing gathered information in order to ensure project stakeholders are in agreement on its elements.
Initiating: Task 6 - correct answerObtain project charter approval from the sponsor, in order to formalize the authority assigned to the project manager and gain commitment and acceptance for the project.
Initiating: Task 7 - correct answerConduct benefit analysis with relevant stakeholders to validate project alignment with organizational strategy and expected business value.
Initiating: Task 8 - correct answerInform stakeholders of the approved project charter to ensure common understanding of key deliverables, milestones, and their roles and responsibilities.
What are the 13 tasks involved in planning a project? - correct answer1. Review project & deliverables
2. Sope management plan
3. Cost management plan
4. Project schedule
5. HR management plan
6. Communications management plan
7. Procurement management plan
8. Quality management plan
9. Change management plan
10. Risk management plan
11. Present project management plan to stakeholders
12. Project kick-off meeting
13. Stakeholder management plan
Planning: Task 1 - correct answerReview and assess detailed project requirements, constraints, and assumptions with stakeholders based on the project charter, lessons learned, and by using requirement gathering techniques in order to establish detailed project deliverables.
Planning: Task 2 - correct answerDevelop a scope management plan, based on the approved project scope and using scope management techniques, in order to define, maintain, and manage the scope of the project.
Planning: Task 3 - correct answerDevelop a cost management plan based on the project scope, schedule, resources, approved project charter and other information, using estimating techniques, in order to manage project costs.
Planning: Task 4 - correct answerDevelop the project schedule based on the approved project deliverables and milestones, scope, and resource management plans in order to manage timely completion of the project.
Planning: Task 5 - correct answerDevelop the human resource management plan by defining the roles and responsibilities of the project team members in order to create a project organizational structure and provide guidance regarding how resources will be assigned and managed.
Planning: Task 6 - correct answerDevelop the communications management plan based on the project organizational structure and stakeholder requirements, in order to define and manage the flow of project information.
Planning: Task 7 - correct answerDevelop the procurement management plan based on the project scope, budget, and schedule, in order to ensure that the required project resources will be available.
Planning: Task 8 - correct answerDevelop the quality management plan and define the quality standards for the project and its products, based on the project scope, risks, and requirements in order to prevent the occurrence of defects and control the cost of quality.
Planning: Task 9 - correct answerDevelop the change management plan by defining how changes will be addressed and controlled in order to track and manage change.
Planning: Task 10 - correct answerPlan for risk management by developing a risk management plan; identifying, analyzing, and prioritizing project risk; creating the risk register; and defining risk response strategies in order to manage uncertainty and opportunity through the project life cycle.
Planning: Task 11 - correct answerPresent the project management plan to the relevant stakeholders according to applicable policies and procedures in order to obtain approval to proceed with project execution.
Planning: Task 12 - correct answerConduct kick-off meeting, communicating the start of the project, key milestones, and other relevant information in order to inform and engage stakeholders and gain commitment.
Planning: Task 13 - correct answerDevelop the stakeholder management plan by analyzing needs, interests, and potential impact in order to effectively manage stakeholders' expectations and engage them in project decisions.
Content preview
STUDYSAGE
Comprehensive PMP Practice Exam: Test Your
Project Management Knowledge
How many project management knowledge areas are there in the PMBOK 6th Edition? - correct answer✔✔10 project management knowledge areas
How many project management processes are covered in the PMBOK 6th Edition? - correct answer✔✔49 project management processes
What are the 10 project management knowledge areas? - correct answer✔✔Communications Management
Cost Management
Integration Management
Quality Management
Procurement Management
Resource Management
Risk Management
Schedule Management
Scope Management
Stakeholder Management
SUCCESS
,STUDYSAGE
What are the 5 project management domains? - correct answer✔✔Initiating (8 tasks)
Planning (13 tasks)
Executing (7 tasks)
Monitoring (7 tasks)
Closing (7 tasks)
What are the 8 tasks involved in initiating a project? - correct answer✔✔1. Assess the project
2. Key deliverables
3. Stakeholder analysis
4. Risks & constraints
5. Project charter
6. Approval of project charter by sponsor
7. Benefit analysis
8. Inform stakeholders
Initiating: Task 1 - correct answer✔✔Perform project assessment based upon available information, lessons learned from previous projects, and meetings
with relevant stakeholders in order to support the evaluation of the feasibility of new products or services within the given assumptions and/or constraints.
Initiating: Task 2 - correct answer✔✔Identify key deliverables based on the business requirements in order to manage customer expectations and direct the
achievement of project goals.
SUCCESS
, STUDYSAGE
Initiating: Task 3 - correct answer✔✔Perform stakeholder analysis using appropriate tools and techniques in order to align expectations and gain support
for the project
Initiating: Task 4 - correct answer✔✔Identify high level risks, assumptions, and constraints based on the current environment, organizational factors,
historical data, and expert judgement, in order to propose an implementation strategy.
Initiating: Task 5 - correct answer✔✔Participate in the development of the project charter by compiling and analyzing gathered information in order to
ensure project stakeholders are in agreement on its elements.
Initiating: Task 6 - correct answer✔✔Obtain project charter approval from the sponsor, in order to formalize the authority assigned to the project manager
and gain commitment and acceptance for the project.
Initiating: Task 7 - correct answer✔✔Conduct benefit analysis with relevant stakeholders to validate project alignment with organizational strategy and
expected business value.
Initiating: Task 8 - correct answer✔✔Inform stakeholders of the approved project charter to ensure common understanding of key deliverables, milestones,
and their roles and responsibilities.
What are the 13 tasks involved in planning a project? - correct answer✔✔1. Review project & deliverables
2. Sope management plan