NAF Contracting Officer Representative
(COR) Course 2024
What are the supplies and/or services to be delivered or performed listed in the contract
considered? - answer Contract deliverables.
Who defines the "initial" contract requirements? - answer Requiring activity.
Who negotiates with potential contractors? - answer Both Contracting Officer and
Contract Specialist.
What is scope of work? - answer What the contractor is being contracted to do.
Quality Assurance Surveillance Plan (QASP) is...? - answer Details how and when the
Government will observe, test/sample, evaluate, and document contractor performance.
Who is primarily responsible for performing the "initial" market research for a purchase
need that is required? - answer Requiring activity.
A Statement of Work is...? - answerA document outlining the work details required to be
performed by contractor.
What are the minimum training requirements to perform COR duties? -
answerContracting Officer's Representative Course and Ethics Training.
The Contracting Officer is the only person that can initiate a deficiency or letter of
concern? - answerTrue.
The COR can initiate contractor remedies on behalf of the Contracting Officer? -
answerFalse.
The COR can request contract deliverables outside the contract scope on behalf of the
Contracting Officer - answerFalse.
The COR should review all cash register readings and reports provided by the
contractor? - answerTrue.
What should a COR do when a contractor is behind in meeting deliverables? -
answerNotify the Contracting Officer.
It is a COR responsibility to ensure NAFI furnished property is maintained and
accounted for in accordance with the contract? - answerTrue.
(COR) Course 2024
What are the supplies and/or services to be delivered or performed listed in the contract
considered? - answer Contract deliverables.
Who defines the "initial" contract requirements? - answer Requiring activity.
Who negotiates with potential contractors? - answer Both Contracting Officer and
Contract Specialist.
What is scope of work? - answer What the contractor is being contracted to do.
Quality Assurance Surveillance Plan (QASP) is...? - answer Details how and when the
Government will observe, test/sample, evaluate, and document contractor performance.
Who is primarily responsible for performing the "initial" market research for a purchase
need that is required? - answer Requiring activity.
A Statement of Work is...? - answerA document outlining the work details required to be
performed by contractor.
What are the minimum training requirements to perform COR duties? -
answerContracting Officer's Representative Course and Ethics Training.
The Contracting Officer is the only person that can initiate a deficiency or letter of
concern? - answerTrue.
The COR can initiate contractor remedies on behalf of the Contracting Officer? -
answerFalse.
The COR can request contract deliverables outside the contract scope on behalf of the
Contracting Officer - answerFalse.
The COR should review all cash register readings and reports provided by the
contractor? - answerTrue.
What should a COR do when a contractor is behind in meeting deliverables? -
answerNotify the Contracting Officer.
It is a COR responsibility to ensure NAFI furnished property is maintained and
accounted for in accordance with the contract? - answerTrue.