IT Project Management Exam 2 || with Errorless Solutions 100%.

Document preview thumbnail
Preview 2 out of 10 pages

While trying to obtain the formal acceptance of the completed project scope and associated deliverables, with whom should the project manager validate the product? a. The sponsor, key stakeholders and customers b. The customers c. The quality control team members d. Then change control board members correct answers a. The sponsor, key stakeholders and customers The scope baseline, which consists of the project scope statement, the WBS, and the WBS dictionary, is used as an input to all the following processes EXCEPT: a. Determine budget process b. Plan procurement management process c. Define activities process d. Develop the team correct answers d. Develop the team Determining if the project scope has been completed by describing project deliverables and the work required to create the detail, enabling the project team to perform more detailed planning, guiding the project teams work during execution, providing the baseline for evaluating changes and other factors relies mostly upon the use of: a. Statement of work b. Project plan c. Project charter d. Project scope statement correct answers d. Project scope statement The major milestones reference some of the key stakeholders are not happy and confident that their requirements are not met. The project manager should have involved them in which of the following processes to ensure their approval of the release? a. Project management plan development b. Identifying constrains c. Validating scope d. Schedule management correct answers c. Validating scope Which one of the following mostly includes the product acceptance criteria that outline requirement a project must meet before stakeholder acceptance the final project or service? a. Quality management plan b. Project scope statement c. Scope management plan d. Requirements management plan correct answers b. Project scope statement Which of the following is NOT true about the define scope process? a. It is the process of developing a comprehensive detailed description of the project and product b. Data analysis is used as a tool and technique in this process

Content preview

IT Project Management Exam 2 || with Errorless Solutions
100%.
While trying to obtain the formal acceptance of the completed project scope and associated
deliverables, with whom should the project manager validate the product?
a. The sponsor, key stakeholders and customers
b. The customers
c. The quality control team members
d. Then change control board members correct answers a. The sponsor, key stakeholders and
customers

The scope baseline, which consists of the project scope statement, the WBS, and the WBS
dictionary, is used as an input to all the following processes EXCEPT:
a. Determine budget process
b. Plan procurement management process
c. Define activities process
d. Develop the team correct answers d. Develop the team

Determining if the project scope has been completed by describing project deliverables and the
work required to create the detail, enabling the project team to perform more detailed planning,
guiding the project teams work during execution, providing the baseline for evaluating changes
and other factors relies mostly upon the use of:
a. Statement of work
b. Project plan
c. Project charter
d. Project scope statement correct answers d. Project scope statement

The major milestones reference some of the key stakeholders are not happy and confident that
their requirements are not met. The project manager should have involved them in which of the
following processes to ensure their approval of the release?
a. Project management plan development
b. Identifying constrains
c. Validating scope
d. Schedule management correct answers c. Validating scope

Which one of the following mostly includes the product acceptance criteria that outline
requirement a project must meet before stakeholder acceptance the final project or service?
a. Quality management plan
b. Project scope statement
c. Scope management plan
d. Requirements management plan correct answers b. Project scope statement

Which of the following is NOT true about the define scope process?
a. It is the process of developing a comprehensive detailed description of the project and product
b. Data analysis is used as a tool and technique in this process

, c. The requirement document is the key output in this process
d. A detailed project scope statement that is created in this process is critical to project success
and build upon the additional detail analysis of requirement, major deliverables, assumptions,
constraints and other factors that are documented earlier in the project correct answers c. The
requirement document is the key output in this process

Product scope describes the features, functions and physical characteristics that characterize a
product, service, or result. Completion of the project scope is measured against which of the
following?
a. Scope statement
b. Project requirements
c. Project objectives
d. Product requirements correct answers d. Product requirements

Verified deliverables are inputs in which of the following scope management processes?
a. Define scope
b. Create WBS
c. Validate scope
d. Control scope correct answers c. Validate scope

Includes the processes required to ensure the project includes all the work required, and only the
work required to complete the project successfully correct answers Project Scope Management

The work performed to deliver a product, services or result with the specified features and
functions correct answers Project Scope

Is a component of the project management plan that describes how project and product
requirements will be analyzed, documented and managed correct answers Project Scope
Management Plan

A component of the project management plan that describes how the project and product
requirement will be analyzed, documented, and managed correct answers Requirements
Management Plan

Is used to provide information on effective requirement collection techniques, especially the
project that are using an iterative of adaptive project development methodology correct answers
Lessons Learned Register

Involves comparing actual or planned products, processes, and practices to those of comparable
organizations to identify best practices, generate ideas for improvement and provide a basis for
measuring performance correct answers Benchmarking

A method of obtaining early feedback on requirement by providing a model of the expected
product before building it correct answers Prototyping

Document information

Uploaded on
December 15, 2024
Number of pages
10
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers
$11.99

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
SirAnton
3.7
(118)
Sold
802
Followers
438
Items
40094
Last sold
6 days ago




Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their exams and reviewed by others who've used these revision notes.

Didn't get what you expected? Choose another document

No problem! You can straightaway pick a different document that better suits what you're after.

Pay as you like, start learning straight away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and smashed it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions