Projects are ________ endeavors.
Temporary
IT projects differ from construction projects in all of the following ways, except
________.
with IT projects, there is more visibility
In which off the following lifecycle phases is a project charter created?
Initiating
Which of the following is not a project characteristic?
Creates resources
Which of the following is not a phase in any project lifecycle?
All of these alternatives are phases of the project lifecycle.
a. Initiating
b. Planning
c. Executing
d. Closing
According to Thomas Friedman, how often does project management get offshored?
Never
If your project starts with existing code, rather than from scratch, then your project is
considered to be a ________.
maintenance project
In which lifecycle phase are schedules, budgets, risks, resources and staffing defined?
Planning
Which of the following is not a project?
Manufacturing an iPhone
Projects create ________.
All of the alternatives are correct
a. products
b. services
c. results
, Which of the following choices is not one of the driving forces behind the increasing
demand for project management?
Development of third world and closed economies
Which of these is not part of the "sociocultural dimension" of project management
according to Larson and Gray?
Resource allocation
A series of coordinated, related, multiple projects that continue over extended time
intended to achieve a goal is known as a ________.
Program
From 1994 to 2009 the phenomena of project lateness or of projects being over budget
were ________.
decreased somewhat (fewer projects were late or over budget)
A professional organization for project management specialists is the ________.
PMI
Integration of all project processes and practices to improve Project Management is due
to ________.
Centralization
An activity is a(n) ________.
Both a. and b. are correct.
a. task
b. step
In Larson and Gray, the two dimensions within project management are ________ and
________.
technical | sociocultural
Which of the following tasks/activities is not considered a project?
Production of automobile tires
What is the name of the software tool that delineates a timeline chart showing all of the
activities and their start and stop dates?
Gantt chart
Which of the following is not typically the responsibility of a project manager?
All of these alternatives are typical responsibilities.
a. Meeting budget requirements
b. Meeting schedule requirements