COMPLETE SOLUTIONS
(R) - ANSWER-Steps requiring verification/inspection
(S) - ANSWER-Steps in an FMA procedure requiring verification by a member of ship's
force
(C) - ANSWER-Steps requiring Cleanliness Inspection by craftsman
(I) - ANSWER-Steps requiring Inspection by QAI or NDT inspector
(CI) - ANSWER-Steps requiring Independent Cleanliness Inspectors (SCI/RCI)
(Q) - ANSWER-Critical quality control point (Q-point)
(V) - ANSWER-Steps requiring verification by a craftsman
(G) - ANSWER-Government notification required
QA form 1 - ANSWER-Material Receipt Control Record
QA form 2 - ANSWER-Material ID/ Control Tag
QA form 3 - ANSWER-Controlled Material Reject Tag
QA form 9 - ANSWER-Maintenance certification record/Re-Entry Control
QA form 10 - ANSWER-Maintenance certification record/ Re-Entry control supplement
sheet
QA form 11 - ANSWER-Controlled work package/re-entry control log
QA form 14 - ANSWER-surveillance/monitoring/ audit discrepancy record
QA form 17 - ANSWER-Test and Inspection record
QA form 18 - ANSWER-Silver Braze Fabrication and inspection record
QA form 18A - ANSWER-Ultrasonic Inspection Record
QA form 20 - ANSWER-Welding in progress control/Nondestructive Test Record