3 sources of liability are: - ✔✔contracts, torts, statutory
contract issues : - ✔✔breach of party, negligence, intentional
injury to a person, or property - ✔✔tort
tort case - ✔✔hertz v. boh bros
forms the laws and regulations - ✔✔statutory
types of liabilities - ✔✔strict
absolute
comparitive
parties to a contract - ✔✔architect, engineer, contractor, owner
what is an architect - ✔✔someone who designs
, who does the architect represent - ✔✔himself, owner during the construction
engineers - ✔✔lead on an industrial prpject
civil engineer - ✔✔designs civil projects
engineer represents - ✔✔himself and owner during the project
when does cm represent the owner - ✔✔during the design
what type of projects do a cm do? - ✔✔all types
other name for general contractor - ✔✔prime contractor
the biggest order of disputes is: - ✔✔change order
on cost plus job the incentive to keep cost down is the CM'S - ✔✔REPUTATION
WHEN WE COMPETITVE BID we add in - ✔✔contingency cost
AIA - ✔✔American institute of architects
the AIA leans toward - ✔✔architect
AGC leans toward the - ✔✔GC
Correct | Verified Solutions
3 sources of liability are: - ✔✔contracts, torts, statutory
contract issues : - ✔✔breach of party, negligence, intentional
injury to a person, or property - ✔✔tort
tort case - ✔✔hertz v. boh bros
forms the laws and regulations - ✔✔statutory
types of liabilities - ✔✔strict
absolute
comparitive
parties to a contract - ✔✔architect, engineer, contractor, owner
what is an architect - ✔✔someone who designs
, who does the architect represent - ✔✔himself, owner during the construction
engineers - ✔✔lead on an industrial prpject
civil engineer - ✔✔designs civil projects
engineer represents - ✔✔himself and owner during the project
when does cm represent the owner - ✔✔during the design
what type of projects do a cm do? - ✔✔all types
other name for general contractor - ✔✔prime contractor
the biggest order of disputes is: - ✔✔change order
on cost plus job the incentive to keep cost down is the CM'S - ✔✔REPUTATION
WHEN WE COMPETITVE BID we add in - ✔✔contingency cost
AIA - ✔✔American institute of architects
the AIA leans toward - ✔✔architect
AGC leans toward the - ✔✔GC