01. Affinity diagrams are useful tools to help analyze and solve what type(s) of problems?
choose the correct answer
a) Unfamiliar problems
b) Structured problems
c) Mathematical models
d) Establishing project flows - Correct Answer-Answer:
a) Unfamiliar problems
02. Which of the following is a primary reason for periodic project reviews?
choose the correct answer
a) To highlight the project team's effort
b) To select either manual or automated reporting methods
c) To review the schedule and costs
d) To assess the team responsibilities and requirements - Correct Answer-Answer:
c) To review the schedule and costs
03. Six sigma project methodology normally begins with what initial step?
choose the correct answer
a) Problem definition
b) Define
c) Project charter
d) Champion approval - Correct Answer-Answer:
b) Define