T/F: The purpose of the collection system is to collect and transport waste to the point of treatment. -
Answers True
T/F: The most important benefit of a collection system is comfort and convenience. - Answers False;
Removal of potential health hazards is most important.
T/F: Parts of a collection system include wastewater lines, wastewater crossings, inverted siphons,
cleanouts, manholes, and lift stations. - Answers True
T/F: If gasoline or solvent odors are detected in a manhole, the operator should bolt and gasket the
cover. - Answers FALSE
T/F: Safety rules for manholes include checking for gases and sufficient oxygen, wearing a lifeline, and
having two workers assisting at the surface. - Answers True
T/F: Clay and PVC are the most common pipe material. - Answers True
T/F: Pipe materials used in collection system construction include polyvinyl chloride, clay, concrete, and
iron. - Answers True
T/F: Grade (or slope) and flow velocity are important to wastewater pipe installation. - Answers True
T/F: For any gravity wastewater, the minimum velocity required to keep solids in suspension is 1 ft/sec. -
Answers False; A velocity of 2 ft/sec is required.
T/F: Pipe should be laid down so that the bell end is facing downstream or downhill. - Answers False; It
should face upstream.
Wastewater flowing into a collection system should come from __________.
A. Storm drainage
B. Homes and businesses
C. Industry
D. B and C - Answers D. B and C
Install wastewater lines no closer to a water line than __________ feet.
A. 7
B. 8
C. 9
, D. 10 - Answers C. 9
OSHA sets standards for shoring, sloping, or trench boxes for trenches _____________ feet or deeper.
A. 6
B. 5
C. 4
D. 3 - Answers B. 5
If the trench is _________ feet or deeper, a means of exit is required.
A. 7
B. 6
C. 5
D. 4 - Answers D. 4
If a ladder is used, it must be portable and extend __________ feet above the trench, in addition to
being secured.
A. 2
B. 3
C. 4
D. 5 - Answers B. 3
A ladder must be within ___________ feet of anyone in the trench.
A. 25
B. 24
C. 23
D. 22 - Answers A. 25
Excavation spoil must be at least ________ feet from the edge of the trench.
A. 5
B. 4
C. 3