BIA stands for ___________. correct answers Business impact analysis
The two primary steps you need to complete before progressing with an RA are defining the assessment
and reviewing previous findings. correct answers True
Malignant Threats are threats that are always present. correct answers True
RPO stands for ____________. correct answers Recovery point objective
A BIA typically identifies the customers and how the organization plans to serve them correct answers
False
RTO stands for ____________. correct answers Recovery time objective
The risk value of an asset is directly proportional to the _______ and _______ of a particular threat
exploiting a vulnerability after considering the controls in place that are protecting the asset. correct
answers Impact, Likelihood
The value of an assessment is only as valuable as the expertise of the experts. correct answers True
A business impact analysis is intended to include all IT functions. correct answers False
Which of the following would not be a common category for asking risk sensitivity questions? correct
answers Skills
Which of the following can be calculated using the values from an annualized rate of occurrence
multiplied by the values from a single loss expectancy? correct answers Annualized loss expectancy
A risk assessment is the same as a risk management program. correct answers False
Low recovery time objectives are _______ but _______. correct answers achievable, costly