Questions and CORRECT Answers
All of the following are true about projects and operations, EXCEPT: - CORRECT
ANSWER- ✔✔Because of their temporary nature, projects cannot help achieve an
organization's long-term goals. Therefore, strategic activities in the organization can be
generally addressed within the organization's normal operations.
Which of the following statements best describe a project? - CORRECT ANSWER- ✔✔A
temporary endeavor undertaken to create a unique product, service, or result.
The collection of generally sequential and sometimes overlapping project phases, whose
name and number are determined by the management and control needs of the organization
or organizations involved in the project, is known as the: - CORRECT ANSWER- ✔✔Project
life cycle.
The term portfolio management refers to: - CORRECT ANSWER- ✔✔The centralized
management of one or more portfolios to achieve strategic objectives.
All of the following are questions that the key stakeholders and project managers should
answer to develop the project success measures, EXCEPT: - CORRECT ANSWER-
✔✔What are the communication requirements?
Which of the following statements best describes Project management? - CORRECT
ANSWER- ✔✔The application of knowledge, skills, tools, and techniques to project
activities to meet the project requirements.
Which of the following statements about the project life cycle and the product life cycle is
NOT true? - CORRECT ANSWER- ✔✔The product life cycle is contained within the
predictive project life cycle.
All of the following are true about project phases and the project life cycle, EXCEPT: -
CORRECT ANSWER- ✔✔Cost and staffing levels are generally steady throughout the
project life cycle.
, The PMBOK® Guide is the standard for: - CORRECT ANSWER- ✔✔Managing most
projects most of the time.
Which of the following statements best describe the term program? - CORRECT ANSWER-
✔✔A group of related projects, subsidiary programs, and program activities managed in a
coordinated manner.
Configuration control focuses on: - CORRECT ANSWER- ✔✔The specification of both the
deliverables and the processes, while change control is focused on identifying, documenting,
and approving or rejecting changes to the project documents, deliverables, or baselines.
Some of the configuration management activities included in the Perform Integrated Change
Control process include all of the following activities, EXCEPT: - CORRECT ANSWER-
✔✔Monitoring changes in resource-leveling heuristics to ensure efficient resource utilization
throughout the life cycle of the project.
Which of the following processes is included in Project Integration Management? -
CORRECT ANSWER- ✔✔Develop project management plan.
Lessons learned documentation generally includes all of the following, EXCEPT: -
CORRECT ANSWER- ✔✔Other types of lessons learned about communications
management.
All of the following are characteristics of the project charter, EXCEPT: - CORRECT
ANSWER- ✔✔It is used primarily to request bids for a project or a specific phase of a
project.
Which of the following is NOT true about tools and techniques of Perform Integrated Change
Control? - CORRECT ANSWER- ✔✔They include project plan updates.
All of the following are Knowledge Management tools and techniques, EXCEPT: -
CORRECT ANSWER- ✔✔Regression analysis.