CQM-C EXAM WITH COMPLETE SOLUTIONS 100%
CORRECT LATEST UPDATE
PASS A+
Characteristics that describe a definable feature of work include: - ANSWER
Cross-referenced listings to the contractors construction schedule that may have more
than one definable feature under a section of the specifications.
The _____________________ consists of daily checks of the work to assure continuing
compliance with contract requirements. - ANSWER Follow-up phase
The Quality Assurance Plan: - ANSWER Is a government management tool establishing
staffing, training, pre-award activities, and surveillance activities.
Testing is a very important component of construction quality management and is
performed by: - ANSWER Both the contractor and the government
The contract allows the contracting officer to take the following action if the contractor
does not provide a satisfactory superintendent: - ANSWER The contracting officer may
require the contractor to perform the work under the personal supervision of the
contractor.
The Quality Control Plan: - ANSWER Provides the basis for quality work and describes
planned quality control procedures.
Tests that are unannounced, randomly performed, and repeat quality control tests are: -
ANSWER Quality Assurance tests
If initial review of the quality control plan shows it to be unacceptable: - ANSWER The
contractor makes changes before acceptance.
, The contractor quality control organization: - ANSWER May vary in size depending on
the work being performed at a point in time.
The Quality Control Plan includes: ANSWER Identification of individual quality quality
control personnel, including name, qualifications, assigned duties, responsibilities and
authorities.
The preconstruction conference and coordination and mutual understanding meeting
(Navy) are: ANSWER Conducted prior to the commencement of any physical
construction work.
A cumulative list of job deficiencies/rework items can be found in: ANSWER A deficiency
tracking system/reworks items list.
What is a purpose of the coordination and mutual understanding and meeting (Navy)? -
ANSWER To review the QC Plan with the contractor.
Which of the following is included in all three phases of the Three Phases of Control. -
ANSWER Safety.
Submittals are: - ANSWER Required to prove the proposed materials, etc. meet the
requirements of the contract.
All submittals for government approval shall be furnished by the _________________ in
time to allow for the review, approval, procurement, delivery, and performance of
preparatory phase for an item before it is needed for construction. - ANSWER
Contractor to the Government
The means for enforcing contract compliance are provided in the: - ANSWER Contract
clauses of the contract.
ENG Form 4288-R, the submittal register: - ANSWER Identifies those submittals
requiring government approval
CORRECT LATEST UPDATE
PASS A+
Characteristics that describe a definable feature of work include: - ANSWER
Cross-referenced listings to the contractors construction schedule that may have more
than one definable feature under a section of the specifications.
The _____________________ consists of daily checks of the work to assure continuing
compliance with contract requirements. - ANSWER Follow-up phase
The Quality Assurance Plan: - ANSWER Is a government management tool establishing
staffing, training, pre-award activities, and surveillance activities.
Testing is a very important component of construction quality management and is
performed by: - ANSWER Both the contractor and the government
The contract allows the contracting officer to take the following action if the contractor
does not provide a satisfactory superintendent: - ANSWER The contracting officer may
require the contractor to perform the work under the personal supervision of the
contractor.
The Quality Control Plan: - ANSWER Provides the basis for quality work and describes
planned quality control procedures.
Tests that are unannounced, randomly performed, and repeat quality control tests are: -
ANSWER Quality Assurance tests
If initial review of the quality control plan shows it to be unacceptable: - ANSWER The
contractor makes changes before acceptance.
, The contractor quality control organization: - ANSWER May vary in size depending on
the work being performed at a point in time.
The Quality Control Plan includes: ANSWER Identification of individual quality quality
control personnel, including name, qualifications, assigned duties, responsibilities and
authorities.
The preconstruction conference and coordination and mutual understanding meeting
(Navy) are: ANSWER Conducted prior to the commencement of any physical
construction work.
A cumulative list of job deficiencies/rework items can be found in: ANSWER A deficiency
tracking system/reworks items list.
What is a purpose of the coordination and mutual understanding and meeting (Navy)? -
ANSWER To review the QC Plan with the contractor.
Which of the following is included in all three phases of the Three Phases of Control. -
ANSWER Safety.
Submittals are: - ANSWER Required to prove the proposed materials, etc. meet the
requirements of the contract.
All submittals for government approval shall be furnished by the _________________ in
time to allow for the review, approval, procurement, delivery, and performance of
preparatory phase for an item before it is needed for construction. - ANSWER
Contractor to the Government
The means for enforcing contract compliance are provided in the: - ANSWER Contract
clauses of the contract.
ENG Form 4288-R, the submittal register: - ANSWER Identifies those submittals
requiring government approval