who is responsible for obtaining NPDES permit coverage for their stormwater
discharges? - ANSWER-construction site operator
what is the primary purpose of erosion and sediment controls? - ANSWER-to protect
surface waters
what is the first step in developing your SWPPP? - ANSWER-evaluate site
what type of filter would commonly be used for inlet protection, - ANSWER-silt fence
rock bags or block and gravel
how far away from storm drains & watercourses should washout areas be located -
ANSWER-50 yards
if the native vegetation cover 50% of the undisturbed ground surface, how much
vegetative coverage must be established on the disturbed ground surface? - ANSWER-
35%
what is the deadline to submit a Notice of Termination, - ANSWER-30 days
who must sign the Notice of Intent - ANSWER-construction site operator
how long is the waiting period before the EPA's Construction General Permit is
considered active? (after NoI is received) - ANSWER-7 days
when can you terminate your permit coverage after a project? - ANSWER-after
stabilization