The shutters and bottom support of non-cantilever slab is removed within a
minimum of ______ days.
7 days
14 days
28 days
21 days Answer - 14 Days
Shotcrete is used in ________
Repairing surfaces
Dam surfaces
Curved surfaces
All of above Answer - All of above
The shutters and bottom support of non-cantilever beam can be removed
within a minimum of ____
7 days
14 days
28 days
21 days Answer - 14 days
Bitumen is used in construction to provide ______
Protective Surface
,Shining surface
Decorative surface
All of above Answer - Protective Surface
First test on concrete is done after ______days
7 days
14 days
28 days
3 days Answer - 7 days
Core samples are taken for finding ____
Tensile strength
Compressive strength
Water absorption
Surface hardness Answer - Compressive strength
Rebound Schmidt hammer test is _____
Destructive test
Non-destructive
Cohesion test
All of above Answer - Non-destructive
Core samples are taken after _____ days
7 days
14 days
28 days
, 10 days Answer - 28 days
Density of Aluminium is _____Kg/m3 in normal temperature.
3500
2700
2500
3000 Answer - 2700
Which type of cement is used in normal slabs ____
SRC
OPC
Non-shrinkage
Rapid hardening Answer - OPC
Density of Steel is _____ Kg/m3
7000
8000
6500
7800 Answer - 7800
Contractors use blankets over fresh concrete to ____
Increase evaporation
Reduce evaporation
Be rapid harden
Avoid sulphate attack Answer - Reduce evaporation