10/7/2024 11:03AM
ENCE 325 Exam Questions With Verified
Answers.
The widening of a state highway is an example of which sector of the construction industry? -
answer✔Infrastructure
Specialty trade contractors are typically hired on the job by which of the following? -
answer✔The Contractor
A construction project is characterized by the following? - answer✔It is unique, It results in
deliverables, and it uses resources
In which of the following stages does the contractor have the major responsibility to coordinate
all necessary tasks associated with that stage? - answer✔Close Out
Which member of the contractor's team is responsible for the day-to-day production activities on
the jobsite? - answer✔The Superintendent
The residential sector of the industry is characterized by which of the following? -
answer✔Projects are fairly low tech
What is the major rating system for green buildings - answer✔LEED
During the start-up and mobilization stage the following activities occur? - answer✔The
contractor moves onto the obsite
The ______ is responsible for the project feasibility stage. - answer✔owner
The outcomes of the bidding and awards stage are ______ ,_______and ______. - answer✔bid
package, bid submittals, and awarding of contract.
A design-build delivery method typically results in the owner having one contract with the
architect and another contract with the contractor. - answer✔False