Written by students who passed Immediately available after payment Read online or as PDF Wrong document? Swap it for free 4.6 TrustPilot
logo-home
Document preview thumbnail
Preview 3 out of 20 pages
Exam (elaborations)

Geotechnical Design Exam Review UPDATED ACTUAL Questions and CORRECT Answers

Document preview thumbnail
Preview 3 out of 20 pages

Geotechnical Design Exam Review UPDATED ACTUAL Questions and CORRECT Answers What are indicator piles. and how do they benefit the foundation design process? - CORRECT ANSWER- Indicator piles are prototype piles that are constructed before the production piles. These prototype piles are typically evaluated using pile driving analyzers, load tests, or other means to evaluate their load capacity. The results of these evaluations are then used to guide the design and construction of the production piles. In many cases, the indicator piles also are used to support the structure.

Content preview

Geotechnical Design Exam Review
UPDATED ACTUAL Questions and
CORRECT Answers
What are indicator piles. and how do they benefit the foundation design process? -
CORRECT ANSWER✔✔- Indicator piles are prototype piles that are constructed before the
production piles. These prototype piles
are typically evaluated using pile driving analyzers, load tests, or other means to evaluate
their load
capacity. The results of these evaluations are then used to guide the design and construction
of the
production piles. In many cases, the indicator piles also are used to support the structure.


Many engineers believe the only disadvantage to over designing pile foundations is the
additional cost of
the pile materials. However, there is another important consequence of over design which can
significantly
affect construction cost and may even make the foundation impossible to build. What is this
consequence and how can it be avoided? - CORRECT ANSWER✔✔- In addition to
increasing materials costs, over designed piles are more difficult to install, thus increasing
labor and equipment costs. In some cases, the additional labor and equipment costs, as well as
the
associated delays in the construction schedule, can be dis proportionally large compared to
the additional
capacity gained. These unnecessary costs and delays can be avoided by more precise designs
and by the used of the various techniques of verification and redesign during construction.
These measures help assure the as built foundation has sufficient capacity and performance,
without being excessively over designed.


Under what circumstances would you most likely require integrity testing of newly-
constructed drilled

shaft foundations? - CORRECT ANSWER✔✔- Integrity testing is especially important
when using the slurry method of construction.

,Explain the difference between the active, at-rest, and the passive earth pressure conditions. -
CORRECT ANSWER✔✔- The at-rest pressure is that which acts on a wall that has not
experienced any lateral displacement or
rotation. In other words, it reflects the horizontal stresses that were present in the undisturbed
ground. The active pressure is that which acts on a wall that has moved a sufficient distance
away from the back fill to
fully mobilize the shear strength of the soil. The passive pressure is that which acts on a wall
that has
moved a sufficient distance into the back fill to fully mobilize the shear strength of the soil.


Which of the three earth pressure conditions should be used to design a rigid basement wall?
Why? - CORRECT ANSWER✔✔- A rigid basement wall should be designed using at-rest
pressure because it has not moved enough to
develop the active condition.


A pre-stressed concrete pile is being driven into a saturated cohesive soil with a hammer blow
count of 17 blows per foot of pile penetration. Unfortunately, the pile driving rig breaks down
before the pile reaches
the required depth of penetration, resulting in a 15-hour delay. Once the rig is repaired, pile
driving
resumes but the blow count is now 25 blows per foot. Explain the primary reason for this
change in blow

count. - CORRECT ANSWER✔✔- Driving of the pile caused large shear stresses in the soil.
Since the soil was a saturated cohesive soil,
positive pore pressures were generated during driving and therefore decreased the effective
stress and
both the end bearing and side friction compared to static loading. During the delay, the soil
had time to
dissipate some of the excess pore pressure generated during driving and the affected soil was
able to
consolidate. The decrease in pore pressure and the consolidation increased the soil strength
and thereby
the pile capacity. This effect is known in practice as ground "setup" or ground "freeze".


Sometimes pile driving contractors use predrilling when installing piles. This method consists
of drilling a

, vertical hole that has a smaller diameter than the pile, then driving the pile into this hole.
Could
predrilling affect the side-friction resistance? Why? Is the diameter of the predrill hole
important? Why? - CORRECT ANSWER✔✔- Predrilling can definitely affect the side-
friction resistance by loosening the soil and by reducing the
lateral earth pressure. Both the size of the predrill hole and its depth are important. The
danger in
predrilling is that it can reduce pile capacity if the predrilling is too long or the diameter of
the hole is
much larger than the pile. Ideally, the hole diameter should be smaller than the pile diameter
and the
length should be kept to a minimum.


Why is it important for drilled shaft contractors to place the concrete soon after drilling the
shaft? What
detrimental effects can occur if the contractor waits too long before placing the concrete? -
CORRECT ANSWER✔✔- There are two potential detrimental effects which can be caused
by delaying concrete placement. The first
is related to reduction in lateral earth pressure. The drilled shaft construction process will
always decrease
the lateral earth pressure around the shaft. The longer time shaft is open, the greater the
reduction, up to
some limit (e.g., the active failure state of the soil around the shaft). The second potential
detrimental
effect is caving and squeezing of soils. The longer the shaft is open, the greater the possibility
of soils
entering the shaft through squeezing or caving. Both of these effects can reduce the capacity.


What is "block failure" in a group of piles and how does it differ from individual failure? -
CORRECT ANSWER✔✔- Block failure is the mode of failure where the pile group and the
soil between the files moves as a unit,
and the side friction resistance is developed along the perimeter of this unit. In contrast,
individual failure
is the mode of failure where each pile fails individually and the side friction occurs along the
side of each

Document information

Uploaded on
October 11, 2024
Number of pages
20
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers
$10.49

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
MGRADES
4.0
(235)
Sold
1539
Followers
108
Items
112237
Last sold
1 day ago



Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions