NICET LEVEL 1 HIGHWAY CONSTRUCTION EXAM NEWEST
2024 WITH COMPLETE QUESTIONS AND CORRECT VERIFIED
ANSWERS (DETAILED ANSWERS) ALREADY GRADED A+ 100%
GUARANTEED TO PASS CONCEPTS!!!
Acceptance - ANSWER-The written acceptance by the Department of the Work.
acceptance testing - ANSWER-Testing conducted by the Department to
measure the degree of compliance to the Contract
actual cost - ANSWER-The computed cost using calculations provided
addendum - ANSWER-A Contract revision or response to a Contractor inquiry
issued after advertisement and before the opening of bids.
as-built quantity - ANSWER-The quantity of a completed Item eligible for
payment
, authorized funding amount - ANSWER-The amount of funds authorized by the
Department for the Contract
Bidder - ANSWER-The individual, firm, partnership, corporation, joint venture,
or any acceptable combination thereof that submits a bid to the Department.
bridge - ANSWER-. A structure, other than a culvert, including supports,
erected over a depression or an obstruction, such as water, highway, or railway,
and having a track or passageway for carrying traffic or other moving loads and
having a length 3 measured along the center of the structure of more than 20
feet between undercopings of abutments or extreme ends of openings for
multiple boxes. Structure dimensions are defined as follows:
bridge length - ANSWER-The overall length measured along the line of survey
stationing from back to back of backwalls of abutments, if present, otherwise
end to end of the bridge floor; but, in no case less than the total clear opening
of the structure
bridge width - ANSWER-The clear width measured at right angles to the
longitudinal centerline of the bridge between the bottom of curbs, or in the
case of multiple height of curbs, between the bottoms of the lower risers or, if
curbs are not used, between inner faces of parapet or railing
Change Order. - ANSWER-A written order issued by the Department to the
Contractor after execution of the Contract authorizing one or more of the
following: 1. Changes in the Work. 2. Modifications in the basis of payment. 3.
Modifications to Contract Time.
Commercially Useful Function - ANSWER-Occurrences in which the
subcontractor is responsible for the execution of a distinct element of the work
of a contract and carrying out its responsibilities by actually performing,
managing, and supervising the work involved, and with respect to materials
2024 WITH COMPLETE QUESTIONS AND CORRECT VERIFIED
ANSWERS (DETAILED ANSWERS) ALREADY GRADED A+ 100%
GUARANTEED TO PASS CONCEPTS!!!
Acceptance - ANSWER-The written acceptance by the Department of the Work.
acceptance testing - ANSWER-Testing conducted by the Department to
measure the degree of compliance to the Contract
actual cost - ANSWER-The computed cost using calculations provided
addendum - ANSWER-A Contract revision or response to a Contractor inquiry
issued after advertisement and before the opening of bids.
as-built quantity - ANSWER-The quantity of a completed Item eligible for
payment
, authorized funding amount - ANSWER-The amount of funds authorized by the
Department for the Contract
Bidder - ANSWER-The individual, firm, partnership, corporation, joint venture,
or any acceptable combination thereof that submits a bid to the Department.
bridge - ANSWER-. A structure, other than a culvert, including supports,
erected over a depression or an obstruction, such as water, highway, or railway,
and having a track or passageway for carrying traffic or other moving loads and
having a length 3 measured along the center of the structure of more than 20
feet between undercopings of abutments or extreme ends of openings for
multiple boxes. Structure dimensions are defined as follows:
bridge length - ANSWER-The overall length measured along the line of survey
stationing from back to back of backwalls of abutments, if present, otherwise
end to end of the bridge floor; but, in no case less than the total clear opening
of the structure
bridge width - ANSWER-The clear width measured at right angles to the
longitudinal centerline of the bridge between the bottom of curbs, or in the
case of multiple height of curbs, between the bottoms of the lower risers or, if
curbs are not used, between inner faces of parapet or railing
Change Order. - ANSWER-A written order issued by the Department to the
Contractor after execution of the Contract authorizing one or more of the
following: 1. Changes in the Work. 2. Modifications in the basis of payment. 3.
Modifications to Contract Time.
Commercially Useful Function - ANSWER-Occurrences in which the
subcontractor is responsible for the execution of a distinct element of the work
of a contract and carrying out its responsibilities by actually performing,
managing, and supervising the work involved, and with respect to materials