BA424 EXAM 2 WITH
COMPLETE SOLUTION
The first step in assembling a project team is to: - Answer identify the required skills.
The greatest project risk occurs when: - Answer The probability of the event is high and
the consequences of the event are high
Three workers complete a full 8-hour day finishing concrete for a terrace. All three
workers are paid $12 an hour and the job bills to the customer $450. What are the total
direct labor costs? - Answer $288
Which statement about scope management is BEST?
A) Scope management must take place during the conceptual development, full
definition, execution, and termination phases.
B) Project goals don't matter in scope management as long as the budget is not
exceeded
C) Scope management is accomplished in a single step by any one project team
member
D) Scope management can begin once a project hits operational level - Answer A
Which adjective is most appropriate for Agile Project Management?
A) Iterative
B) Sequential
C) Linear
D) Hirsute - Answer A
Most project resources are negotiated with: - Answer Project managers
Risk Management is a ________-stage process - Answer four
The order of magnitude cost estimate is used as: - Answer the first estimate in the life
cycle of a project
The statement of work should contain which of the following:
A) Information on the key objectives for the project.
COMPLETE SOLUTION
The first step in assembling a project team is to: - Answer identify the required skills.
The greatest project risk occurs when: - Answer The probability of the event is high and
the consequences of the event are high
Three workers complete a full 8-hour day finishing concrete for a terrace. All three
workers are paid $12 an hour and the job bills to the customer $450. What are the total
direct labor costs? - Answer $288
Which statement about scope management is BEST?
A) Scope management must take place during the conceptual development, full
definition, execution, and termination phases.
B) Project goals don't matter in scope management as long as the budget is not
exceeded
C) Scope management is accomplished in a single step by any one project team
member
D) Scope management can begin once a project hits operational level - Answer A
Which adjective is most appropriate for Agile Project Management?
A) Iterative
B) Sequential
C) Linear
D) Hirsute - Answer A
Most project resources are negotiated with: - Answer Project managers
Risk Management is a ________-stage process - Answer four
The order of magnitude cost estimate is used as: - Answer the first estimate in the life
cycle of a project
The statement of work should contain which of the following:
A) Information on the key objectives for the project.